Dam overtopping risk assessment considering inspection program

Jan-Tai KuoÆ Yung-Chia Hsu Æ Yeou-Koung Tung Æ

Keh-Chia YehÆ Jian-De Wu

Published online: 13 March 2007

Springer-Verlag 2007

Abstract Safety inspection of large dams in Taiwan is conducted every 5 years. The practice does not take into consideration uncertainty of dam conditions. The goal of this study is to determine the optimal dam inspection interval under the consideration of overtopping risk incorporating uncertainty gate availability. In earlier stud-ies, assessment of overtopping risk only considered the uncertainties in reservoir properties and natural random-ness of hydrologic events without giving much thought to the availability of spillway gates. As a result, the over-topping risk could be underestimated. In this study, an innovative concept is proposed to evaluate dam overtop-ping by taking into account spillway gate availability. The framework consists of three parts: (1) evaluation of con-ditional overtopping risk for different numbers of mal-functioning spillway gates; (2) evaluation of spillway gate availability; and (3) dam inspection scheduling. Further-more, considerations are given to overtopping risk, inspection cost, and dam break cost for determining the

optimal inspection schedule. The methodology is applied to the Shihmen Reservoir in Taiwan and to evaluate its time-dependent overtopping risk. Results show that overtopping risk considering the availability of the spillway gates is higher than the one without considering the availability of the spillway gates.

Keywords Dam safety Dam inspection  Overtopping risk Gate availability  Fault tree

1 Introduction

Taiwan is located in a region plagued by frequent occur-rences of typhoons and earthquakes. Dam safety is a major concern to the general public. As dam failure does not occur suddenly, signs of deterioration could be detected by regular inspection. Therefore, a dam owner has to consider the trade-off between facing a high risk of dam break and engaging in a program of more frequent inspections.

According to the International Commission on Large Dams (ICOLD 1973), overtopping causes about 35% of all earth dam failures; seepage, piping, and other causes make up the rest. Various studies (Langseth and Perkins 1983; Resendiz-Carrillo and Lave 1987; Karlsson and Haimes

1988a, b, 1989; Haimes et al.1988) have proposed proce-dures to assess the safety of dams. The National Research Council (NRC 1988) has recommended general approaches to estimating probability distributions associated with extreme precipitation and runoff. In earlier studies (Askew et al. 1971; Cheng et al. 1982; Afshar and Marino1990; Meon1992; Pohl1999; Hsu and Kuo2004; Kwon and Moon

2006), overtopping risk that is assessed without considering the possible occurrence of malfunctioning spillway gates could result in potential underestimation of the risk. In this

J.-T. Kuo (&)

Department of Civil Engineering and Hydrotech Research Institute, National Taiwan University, Taipei, Taiwan e-mail: kuoj@ntu.edu.tw

Y.-C. Hsu J.-D. Wu

Department of Civil Engineering,

National Taiwan University, Taipei, Taiwan Y.-K. Tung

Department of Civil Engineering,

Hong Kong University of Science and Technology, Kowloon, Hong Kong

K.-C. Yeh

Department of Civil Engineering, National Chiao Tung University, Hsinchu, Taiwan

(2)

study, a method that takes into account the availability of spillway gates is proposed to evaluate overtopping risk. The overtopping risk is assessed by considering the random numbers of malfunctioning spillway gates that are not operable during flood events.

Numerous studies using risk and uncertainty analysis have been conducted over the years for safety evaluation of hydraulic structures. Tung and Mays (1981) applied the first-order second-moment (FOSM) method to estimate static and time-dependent reliability for a storm sewer system. Cheng et al. (1982) and Cheng (1993) applied the advanced first-order second-moment (AFOSM) method and fault tree analysis to evaluate dam overtopping risk. Yeh and Tung (1993) applied the FOSM method to evaluate the uncertainty and sensitivity of a pit-migration model.

In this study, reservoir routing, flood frequency analysis, availability model (Tang and Yen 1991), and various uncertainty analysis methods, such as the mean-value FOSM (MFOSM) and the Harr’s (Harr 1989) point estimation (HPE) methods, are applied to estimate overtopping risk. This study consists of three parts (see Fig.1): (1) evaluation of time-dependent availability of a single spillway gate; (2) evaluation of overtopping risk under the condition of mul-tiple malfunctioning spillway gates; and (3) determination of

optimal inspection scheduling considering overtopping risk by minimizing the annual total expected cost.

2 Availability model

A system is classified as available if the operational con-dition of a system is satisfactory; otherwise, it is considered unavailable (see Fig. 2) and requiring repair. The avail-ability of a system is defined as the fraction of time that the system is operating satisfactorily. The availability A of a dam system in an inspection cycle can be expressed as (Tang and Yen 1991):

A¼ PSð Þ þs X 0

sþ srPFð Þ;s ð1Þ

where PSð Þ and PFs ð Þ are the probabilities of a dam systems operating under satisfactory state S and unsatisfactory state F, respectively; X¢ is the time-to-breakdown in an inspection cycle which includes a breakdown; s and sr are the in-spection interval and repair time, respectively. Generally, the availability model could be applied to different systems and it is applied herein to a spillway gate system. The availability of a spillway gate is the probability of it working under satisfactory conditions; conversely, unavailability is the probability of a spillway gate being inoperative.

If a spillway gate system is operating in multiple breakdown-repair cycles, the expected availability A can be written as (Tang and Yen 1991):

A¼ 1  sr sþ srFXð Þ s 1 sþ sr Z s 0 FXð Þdx;x ð2Þ

where FXð Þ is the cumulative distribution function ofx unsatisfactory time.

Since all deficiencies might not be identified completely, Ang and Tang (1984) considered imperfect detection and

Dambreak cost

Dam inspection scheduling

Inspection cost

Optimal inspection interval Data collection

Deficiency detectability p

Availability model

Repair compliance probability q Mean breakdown timeof a spillway gate

Binomial distribution

Overtopping risk Hydrological frequency analysis

QT(T-year return period flood)

Reservoir routing and risk analysis

Conditional overtopping risk ) , | (OT lQ Pf ) (OT Pf opt τ Gate availability

Fig. 1 Flow chart for evaluating the optimal inspection interval. Note: Here Pf(OT|l,Q) represents overtopping risk varying with flood frequency due to the number l of malfunctioning spillway gates; and Pf(OT) represents overtopping risk

Dam operating under satisfactory conditions : inspection interval

: repair interval

: random breakdown time

: random breakdown time which includes a breakdown

t tr t t X X= ′ X Xt r t X X′ 1 t t2 t3 ′ 3 t

(3)

derived the expected availability, assuming that the defi-ciency detectability increased exponentially with the inspection frequency, as (Ang and Tang1984; Tang and Yen

1991):

where p is the deficiency detectability; and q is the repair compliance probability. Each term in Eq. 3 corresponds to a path in Fig.3, representing the probability of the corre-sponding path. The first term is the probability PSð Þ cor-s responding to the upper path. The second term is related to the path F-D-R in Fig.3, where its availability is X0=sþ sr with path probability PFð Þpq: By collecting terms, Eq. 3s becomes

Assuming that X¢ has an exponential distribution with a mean value l for a single spillway gate that does not age; the expected availability (Tang and Yen1991) can be expressed as:

In some cases, a system might age due to internal and external deterioration of its physical conditions. The treatment of aging systems can be found in Ang and Tang (1984).

3 Overtopping risk assessment incorporating gate availability

Referring to Fig.4, evaluation of overtopping risk involves uncertainty analysis in reservoir routing by considering uncertainties in the operation policy, flow input, reservoir geometric information, and others. In earlier studies of overtopping risk, the unavailability of the gates was not

considered rendering an underestimation of overtopping risk.

In this study, a procedure for evaluating overtopping risk is proposed which involves (a) collection of annual A¼ PSð Þ þ PFs ð Þ ps X 0 sþ srqþ X1 n¼2 X0 nsþ srq 1=n P n1 i¼1 1 q 1=i     " # ( þX 1 m¼2 p1=m m1P j¼1 1 p 1=j     X0 msþ srqþ X1 n¼2 X0 nþ m  1ð Þ ½ s þ srq 1=nY n1 i¼1 1 q1=i   " #) : ð4Þ A¼ es=lþ 1  es=l s lþ 1     p s q lþ sr l þX 1 n¼2 q1=nn1Q i¼1 1 q1=i   nlsþsr l 2 6 6 4 3 7 7 5 8 > > < > > : þX 1 m¼2 p1=m Y m1 j¼1 1 p1=j   " # q ms l þ sr l þX 1 n¼2 q1=nn1Q i¼1 1 q1=i   nþm1 ð Þs l þ sr l 2 6 6 4 3 7 7 5 9 > > = > > ; : ð5Þ A¼ PSð Þ þ PFs ð Þs ( X0 sþ srpqþ X0 2sþ srpð1  qÞq 1=2 þ      þ " X0 2sþ srð1  pÞp 1=2qþ X0 3sþ srð1  pÞp 1=2ð1  qÞq1=2þ    #) ð3Þ

(4)

peak discharge data and establishment of the flow-fre-quency relationship; (b) using reservoir routing to calcu-late the highest water level for floods of varying frequencies under different numbers of malfunctioning gates; and (c) defining the performance function for risk analysis. Note that the rating curve of flow release facil-ities needs to be defined according to the number of malfunctioning gates. The details of the procedure are described as follows.

3.1 Reservoir routing

The reservoir routing is done according to the discrete form of the continuity equation:

Itþ Itþ1 2  Otþ Otþ1 2 ¼ Stþ1 St Dt ; ð6Þ

where Itand It+1represent reservoir inflows at times t and t + 1; Otand Ot+1are reservoir outflows; Stand St+1are reservoir volumes; andDt is the routing interval. Using Eq. 6, one can compute the water level hydrograph and the highest level in the reservoir during a flood event. Under different numbers of malfunctioning gates the reservoir water surface hydro-graph can be computed by adjusting the rating curve of water release facilities corresponding to the number of malfunc-tioning gates on the spillway.

3.2 Risk analysis

The failure of an engineering system can be defined as the loading to the system (L) exceeding the resistance of the system (R). The reliability of a hydraulic infrastructure can be defined as the probability that R > L, i.e.,

a¼ P L  R½ ; ð7Þ

where P½  represents the probability. Therefore, the risk a¢ can be represented as:

a0¼ P L[R½  ¼ P Z\0½  ¼ 1  a: ð8Þ The reliability can also be written as P Z½  0 in which Z is the performance function definable by Z = R – L, (R / L) – 1, or ln(R/L). Let P OTjl; qð Þ represent dam overtopping risk under a specific flood with peak discharge q and l malfunctioning gates. Then, Eq. 8 can be expressed as P OTjl; qð Þ ¼ P Z l; q½ ð Þ\0 ¼ P HC½  HWðl; qÞ\0; ð9Þ where HCand HWrepresent dam crest height and the highest water level during a flood event, respectively. Note that randomness of Hw, under specific q and l, is due to uncertainties in reservoir geometry, spillway rating curve,

A S D R R D F ( )τ S P p ( )τ F P q q − 1 p − 1 First inspection interval τ First repair interval r τ τ Second inspection interval S: satisfactory State

F: unsatisfactory state or Breakdown

D: deficiency detected D: deficiency not detected R: repair work performed R: repair work not performed

Fig. 3 Event tree of deficiency-detection-repair scenario in dam inspection Numbers of malfunctioning spillway gates Operation rule Overtopping AND Reservoir stage Outflow

Initial stage Inflow Reservoir

geometry AND

AND

Fig. 4 Simple fault tree of dam failure due to overtopping considering malfunctioning spillway gates

(5)

etc. The annual dam overtopping risk conditional on l malfunctioning gates can be calculated by

P OTjlð Þ ¼ Z 1

0

P Z l; q½ ð Þ\0fQð Þdq;q ð10Þ where fQ(q) denotes the probability density function of the annual peak discharge Q. Equation 10 can be approximated in discrete form as

P OTjlð Þ ffiX 1

n¼1

P Z l; q½ ð Þ\0DFQð Þ;qn ð11Þ

in which DFQð Þ represents the nth incremental proba-qn bility.

Assuming the number of malfunctioning spillway gates follows a binomial distribution, the dam overtopping risk incorporating gate availability can be calculated as

PðOTÞ ¼X K

l¼0

CKll  Ulgate AKlgate P OTjlð Þ; ð12Þ

where P(OT) is the annual overtopping risk; ClK – l the binomial coefficient; K and l the total number of spillway gates and number of malfunctioning gates, respectively; Ugateand Agatethe unavailability and availability of a single gate that can be determined by Eq. 5; and P(OT|l) is the conditional overtopping risk under l malfunctioning gates on the spillway.

3.3 Uncertainty analysis of overtopping performance function

The main purpose of uncertainty analysis is to quantify the statistical features of system outputs or responses as af-fected by the stochastic basic parameters in the system. The selection of appropriate method depends on the nature of the problem at hand, including availability of information, model complexity, and type and accuracy of results desired (Tung and Yen2005). In this study, the MFOSM and HPE method are used to obtain the first two moments of the performance function defining dam overtopping risk. 3.3.1 Mean-value first-order second-moment (MFOSM)

method

The MFOSM method assumes that the uncertainty features of a random variable can be represented by its first two statistical moments. This method is based on the Taylor series expansion of the performance function linearized at the mean values of the random variables.

For a performance function Z involving k random vari-ables as

Z ¼ g Xð Þ; ð13Þ

where Xt¼ X

1; X2; . . . ; Xk

 

is a row vector containing k random variables. Its Taylor series expansion at the mean values of the k random variables can be expressed as:

Z¼ g xð Þ þX k i¼1 Xi xi ð Þ@g @Xi X¼x þX k i¼1 Xk j¼1 Xi xi ð Þ Xj  xj @ 2g @Xi@Xj X¼x þ H.O.T:; ð14Þ in which xt¼ x 1; x2; . . . ; xk

ð Þ represents a row vector containing the mean values of k random variables; H.O.T. represents the higher-order terms; the partial derivative terms are sensitivity coefficients denoting the rates of change in the model output Z with respect to the unit change of the corresponding variable at x: For most practical applications information on higher-order moments and cross-product moments are not easily available and, thus, the first-order approximation of Z is used (Tung and Yen2005).

Z  g xð Þ þX k i¼1 Xi xi ð Þ@g @Xi X¼x : ð15Þ

Hence, the mean and variance of Z by the first-order approximation can be approximated, respectively, as

E Zð Þ  z ¼ g xð Þ; ð16Þ Var Zð Þ  Var X k i¼1 @g @Xi   Xi xi ð Þ ( ) : ð17Þ

3.3.2 Harr’s point estimation (HPE) method

Harr (1989) proposed an alternative probabilistic point estimation method, which requires 2k model evaluations for a performance function involving k random variables. A multivariate model Z ¼ g Xð Þ involving 2k points for function evaluation by the HPE method is:

xi¼ x  ffiffiffi k p

D1=2x vi for i¼ 1; 2; . . . ; k; ð18Þ in which xi represents the vector of coordinates of the 2k points for function evaluation in the parameter space cor-responding to the ith eigenvector vi; x¼ xð 1; x2; . . . ; xkÞ

t ; a vector of means of k basic random variables; and Dx is a diagonal matrix of variance of k random variables.

Based on the 2k points determined by Eq. 18, the per-formance function values at each of the 2k points can be computed. Then, the rth-order moment of the performance function Z can be calculated by

(6)

zr i ¼ zr iþþ zri 2 ¼ grðxiþÞ þ grðxiÞ 2 for i¼ 1; 2; . . . ; k; r ¼ 1; 2; . . . ; ð19Þ E Zð Þ ¼r Pk i¼1kizri k for r¼ 1; 2; . . . ; ð20Þ where ki is the ith eigenvalues associated with the corre-lation matrix.

4 Dam inspection scheduling

The expected total annual cost (TC) used herein for a dam inspection program can be expressed as

TC¼ P OTð ÞC þwp d

s ; ð21Þ

in which C is the annual damage cost; s the inspection interval; p the deficiency detectability; w and d being constants. The first term is the expected annual damage cost and the second term is the annual inspection cost with wpdbeing the total inspection cost. The expected TC varies with the inspection interval s; the optimal inspection interval can be determined by minimizing TC.

Equation 21 indicates that the inspection cost goes up with the increasing p-value. For p = 1.0, w is the cost associated with perfect (or nearly perfect) detectability, which is rarely achievable in practice.

5 Relevant parameters in dam inspection scheduling 5.1 Deficiency detectability p

Deficiency detectability p could be determined from the records of dam-safety inspections or from experienced dam inspectors. Generally, deficiency detectability de-pends on factors including, but not limited to, cost, manpower, experience of the inspectors, equipment used, and/or the uncertainties involved in the dam system. In practice, it is practically impossible to detect all defi-ciencies in dam safety inspection, i.e., there is no perfect detection, no matter how costly the inspection is. This indicates that an upper limit exists for p.

Ang and Tang (1984) proposed a deficiency detect-ability p to describe the detection probdetect-ability of an inspection. The value of p can be estimated from inspection cost, the past experiences, and the quality of the inspector. An assessment method was first proposed by Kuo et al. (2004) to evaluate the deficiency

detect-ability from the information on cost, the past experi-ences, and the quality of the inspectors. The value of the deficiency detectability p used in this study is 0.74 estimated by Kuo et al. (2004).

5.2 Repair compliance probability q

Repair compliance probability q is the degree of willing-ness of dam owners to do the repair work as suggested by inspection. It can be determined from the repair records of a dam or from the degree of importance that the dam owner assigns to that repair. A greater value of q means that the dam owner would commit sufficient funds to repair the dam quickly. A small value of q, conversely, indicates the dam owner is less willing to repair the dam.

In the study of Kuo et al. (2004), the repair compliance probability was estimated according to the ratio of the re-paired items to the total suggested repair items. If more items are being repaired in a short period of time, the value of q will be larger. Conversely, if items are not being re-paired in a short time, the value of q will be small. The value of the repair compliance probability q used in this study is 0.73 estimated by Kuo et al. (2004).

5.3 Dam break cost C

The dam break cost includes the cost of the dam and the economic losses associated with the incidence. Economic losses can be tangible and intangible. Tangible losses in-clude direct and indirect losses whereas intangible damages include losses, which could not be measured in monetary terms, such as human life, productivity, psychological trauma, etc. Direct losses mainly are the damage to prop-erties including crops, buildings, facilities, goods, and

Direct loss Indirect loss

Economic losses K (ratio of indirect loss to direct loss) Inundation area and depth for

different land uses

Land use Inundation area and depth

Inundation area-damage relation

Flow routing after dam break

(7)

materials, etc. Indirect losses involve those caused indi-rectly by floods including plant shutdown due to losses of electricity, decline of land value or rental fee, etc. In this study, only tangible losses are considered in the estimation of the economic losses due to dam failure.

Economic losses, generally, increase with inundation depth and the extent of the flooded area. Depending on the scale effect and landform, one can use a 1D or 2D model to simulate the inundation area and depth. Depending on the land use and gross domestic product, the economic losses will be different in residential, commercial or industrial areas at the same inundation depth. The procedure to assess the cost of inundation is shown in Fig.5, which involves (1) dam break flow routing; (2) estimating the inundation area and depth; and (3) estimating economic losses.

6 Case study

6.1 Shihmen Reservoir

The Shihmen Reservoir, in operation since 1964, is located in the upstream reaches of Dahan Creek, a tributary of the Tanshui River in northern Taiwan. The reservoir has a drainage area of 763.4 km2 and an active storage of 2.5 · 108 m3 making it the third largest reservoir in

Taiwan. The functions of the reservoir include irrigation, domestic water supply, hydropower generation, and flood control. Relevant information on the Shihmen Dam is can be found in Table1.

6.2 Spillway gate availability

Considering the spillway gate system as a non-aging sys-tem, the time-dependent availability or unavailability of a single gate can be evaluated by Eq. 5. To illustrate the proposed procedure the mean breakdown time of a single gate on a spillway considered was assumed to be 20, 30, and 40 years, along with the deficiency detectability p = 0.74, and repair compliance probability q = 0.73 (Kuo et al. 2004). Figure 6 indicates that the unavailability or breakdown probability of a single spillway gate increases with time and the overtopping risk would increases with it as a result. With a larger deficiency detectability, the availability of a single spillway gate can remain at a higher value than for cases with smaller deficiency detectability (see Fig.6).

Assuming the occurrence of malfunctioning spillway gates follows a binomial distribution, it can be calculated by the terms between the summation sign and the term of overtopping risk in Eq. 12. Knowing the binomial coeffi-cients, namely, the total number of spillway gates, the number of the malfunctioning gates, and gate availability, and unavailability, the occurrence of malfunctioning spillway gates can be evaluated. For illustration, some of the results are shown in Fig. 7. The occurrence probability of zero-malfunctioning gate decreases with time while that of non-zero malfunctioning gates increases with time due to the time-dependent decreasing availability and increas-ing unavailability of spillway gates. Consequently, over-topping risk increases with time due to the decreasing availability of spillway gates.

Table 1 Key information on the Shihmen Dam

Facility Crest elevation or capacity

Non-overflow section 252.1 m

Overflow section 235.0 m

Height 133.0 m

Crest length 360.0 m

Spillway 11,400 m3/s

Tunnel spillway (diameter 10 m) 2,400 m3/s

0.6 0.7 0.8 0.9 1.0 10 11 12 13 14 15 16 17 18 19 20 Time (year) Availability p=0.54 p=0.74 p=0.94 0 1 2 3 4 5 6 7 8 9

Fig. 6 Availability of a single spillway gate with l = 30 years and a repair compliance probability q = 0.73

1.0E-14 1.0E-13 1.0E-12 1.0E-11 1.0E-10 1.0E-09 1.0E-08 1.0E-07 1.0E-06 1.0E-05 1.0E-04 1.0E-03 1.0E-02 1.0E-01 1.0E+00 0 10 11 12 13 14 15 16 17 18 19 20 Time (year) Occ u rrence Probability l=0 l=4 l=6 l=8 9 8 7 6 5 4 3 2 1

Fig. 7 Time-dependent occurrence probability of l malfunctioning gates

(8)

6.3 Overtopping risk

In this study, the annual peak discharge records were col-lected from 1962 to 2002 by the Shihmen Reservoir Operation Administration. Using chi-square test the best fit distribution is the Gumbel distribution.

Peak discharges of different return periods found by frequency analysis were converted into hydrographs by the unit hydrograph derived according to the records collected from 1962 to 2002. The hydrograpghs of different return periods were then routed through the Shihmen Reservoir considering current operation rules. The highest reservoir water levels under floods of different return period were evaluated for different numbers of malfunctioning spillway gates. The MFOSM and HPE methods with consideration of three uncertain factors (namely, reservoir geometry, spillway rating curve, and the error of the reservoir routing model) are adopted to calculate the dam overtopping risk by Eqs. 9–11. Table2 shows the conditional overtopping risk increases due to an increase in the number of mal-functioning spillway gates, in which the risk values are the average calculated by the MFOSM and HPE methods. Figure8demonstrates the comparison of overtopping risk values with and without considering malfunctioning spill-way gates and it clearly indicates an underestimation of overtopping risk by neglecting consideration of malfunc-tioning spillway gates.

Since the time-dependent availability of a single gate on spillway and the dam overtopping risk under different numbers of malfunctioning gates have been evaluated, the annual overtopping risk of Shihmen Dam can be computed by Eq. 12. Figure9, which depicts the results under p = 0.74 and q = 0.73 for three mean gate breakdown times: l = 20, 30, and 40 years, shows that the overtop-ping risk increases with time due to increasing time-dependent unavailability of the spillway gates. Moreover,

Fig.9shows that the mean gate breakdown time influences the availability of spillway gates and the overtopping risk with time.

6.4 Cost of dam break

The cost of dam break consists of two components: the reconstruction cost of Shihmen Dam and economic losses due to down-stream inundation. The reconstruction cost of Shihmen Dam is estimated by calculating its present value considering a 5% interest rate. Shihmen Reservoir was completed in 1964, and its total present value in 2000 is estimated to be NT$ 18.6 billion.

The economic losses include direct and indirect losses. The values of direct and indirect losses in different areas affected by dam failure are concluded in Table 3. Total economic losses due to inundation are NT$ 4.26 billion. Detail calculation of the cost associated with Shihmen Dam failure can be found in Kuo et al. (2004). Therefore, the total dam break cost is estimated to be NT$ 22.86 billion.

Table 2 Overtopping risk considering l malfunctioning spillway gate(s)

Numbers of malfunctioning spillway gates, l

Overtopping risk due to malfunctioning gate(s), P(OT|l)

0 1.5909 · 10–5 1 3.3575 · 10–5 2 1.3409 · 10–4 3 1.2349 · 10–3 4 6.5962 · 10–3 5 4.9830 · 10–2 6 1.6478 · 10–1 7 5.3245 · 10–1 8 9.7167 · 10–1 1.0E-05 1.0E-04 1.0E-03 1.0E-02 1.0E-01 1.0E+00 0 9 10 11 12 13 14 15 16 17 18 19 20 Time (year) Probability l=0 l=2 l=4 l=6 l=8 8 7 6 5 4 3 2 1

Fig. 8 Comparison of overtopping risk with and without considering malfunctioning spillway gates

1.0E-05 1.0E-04 1.0E-03 1.0E-02 1.0E-01 1.0E+00 10 11 12 13 14 15 16 17 18 19 20 Time (year) Risk m=20 m=30 m=40 0 1 2 3 4 5 6 7 8 9

Fig. 9 Time-dependent overtopping risk considering malfunctioning spillway gate under p = 0.74, q = 0.73, and l = 20, 30, and 40 years

(9)

6.5 Inspection scheduling

In determining dam inspection scheduling, the annual total cost TC for Shihmen Dam can be expressed as Eq. 22.

TC¼ P OTjs; p; qð ÞC þ4:6 e 9:52p

s ; ð22Þ

where P OTjs; p; qð ÞC is the product of TC of dam break and overtopping risk evaluated by Eq. 12; the second cost component is the annual inspection cost, a function of inspection cost which is roughly adjusted and estimated based upon the inspection records of six different large dams in Taiwan collected by Kuo et al. (2004); and s is the inspection interval. TC is an U-shaped curve from which one can determine optimal inspection interval sopt, corre-sponding to the lowest point on the TC-curve. Adopting an inspection interval shorter than sopt indicates that a lower risk of dam failure but a higher value of inspection cost; conversely, adopting an inspection interval longer than sopt indicates that a higher risk of dam failure but a lower value of inspection cost.

With p = 0.74, q = 0.73, and a mean breakdown time l = 30 years, the optimal inspection interval for Shihmen Dam is about 5.3 years (see Fig.10) corre-sponding to the minimum TC. One can observe that for an inspection interval between 5 and 8 years (see Fig.10) the total cost curve around the minimum is rather flat. How-ever, a larger inspection interval is would be associated

with taking a higher risk of dam failure. One should con-sider the trade-off between the two.

Figure10 shows that the optimal inspection interval increases with deficiency detectability p under a fixed re-pair compliance probability q. Considering the effect of the mean gate breakdown time, a longer mean gate breakdown time results in a longer optimal inspection interval for a fixed p and q. Furthermore, Fig. 10also shows that a higher p-value flattens the bottom of U-shaped TC-curve for a fixed q and mean gate breakdown time. This implies that one can determine a more flexible inspection interval as the total cost curve is rather constant around the minimum. Similarly, Fig.11 shows that the inspection interval in-creases with repair compliance q under a fixed deficiency detectability p. The optimal inspection interval varies from 4.4 to 6.0 years with q-values varying from 0.6 to 1.0. Moreover, the annual cost of dam break increases with a decrease in q-value. Therefore, with higher values of p and q, the optimal inspection interval increases.

Dam break cost C is the other important factor. Figure12 shows the optimal inspection interval varies from 4.8 to 5.5 years with dam break cost varying from 0.8 to 1.2 times of C for p = 0.74, q = 0.73, and a mean breakdown time of 30 years for a single gate. Some suspect that dam break cost would be much higher than expected; Fig.13 shows the optimal inspection intervals with dam break cost varying from 0.2 to 5 times of C. The results show that a higher dam break cost C would result in decreasing optimal inspection intervals. Table4shows that

Table 3 Economic losses due to inundation in different regions (unit: million NT$)

Losses Taipei county Taipei city Taoyuan county Summation

Direct 1,543.33 291.01 1,417.35 3,251.69 Indirect 505.86 96.73 408.43 1,011.02 Total 2,049.19 387.74 1,825.78 4,262.71 1.0E+06 1.0E+07 1.0E+08 1.0E+09 0 10 11 12 13 14 15 16 17 18 19 20

Inspection interval (year)

Total Cost (NTD) p=0.94 p=0.84 p=0.74 p=0.64 p=0.54 9 8 7 6 5 4 3 2 1

Fig. 10 Sensitivity of optimal inspection interval for Shihmen Dam with respect to deficiency detectability under q = 0.73 and l = 30 years

1.0E+07 1.0E+08 1.0E+09

0 2 9 10 11 12 13 14 15 16 17 18 19 20

Inspection interval (year)

Total cost (NTD) q=0.53 q=0.63 q=0.73 q=0.83 q=0.93 1 3 4 5 6 7 8

Fig. 11 Sensitivity of optimal inspection interval for Shihmen Dam with respect to repair compliance probability under p = 0.74 and l = 30 years

(10)

the sensitivity of the inspection interval to p, q, and C ranges from 80 to 120%. Results show that p is the most sensitive factor because a larger value of p would corre-spond to higher inspection cost. Figure14shows that the optimal inspection interval would increase with increasing p and q-values.

7 Summary and conclusions

Earlier studies on the assessment of dam overtopping risk that consider only the uncertainties in the reservoir prop-erties and natural randomness of hydrologic events without taking into account the spillway gates availabilities could underestimate dam overtopping risk. In this study, a framework is proposed to evaluate time-dependent over-topping risk considering the availabilities of spillway gates. The framework includes (1) evaluation of conditional overtopping risk under different numbers malfunctioning spillway gates; (2) evaluation of spillway gate availability; and (3) dam inspection scheduling. The time-dependent overtopping risk is assessed by considering the random

numbers of malfunctioning spillway gates that are not operable during flood events. Furthermore, considerations are given to overtopping risk, inspection cost, and dam break cost for determining the optimal inspection schedule. Results show that overtopping risk considering the availability of spillway gates is greater than the risk com-puted without considering the availability of spillway gates. Moreover, the optimal inspection interval for Shihmen Reservoir is estimated to be about 4.7, 5.3, and 6.6 years for p = 0.74, q = 0.73, and the mean gate breakdown time of l = 20, 30, and 40 years, respectively. In Taiwan, government policy requires a dam inspection interval to be carried out every 5 years. Based on this study, an optimal inspection interval can be determined according to different conditions for a dam.

8 Recommendations

Two types of error associated with flood frequency analysis (quantile estimation) are not considered in this study. The first type arises from the assumption that the observations follow a particular distribution. The second type is the error inherent in the parameter estimates from small samples. The uncertainties for each return period of flood might affect overtopping risk and then affect the optimal dam 1.0E+07

1.0E+08 1.0E+09

9 10 11 12 13 14 15 16 17 18 19 20 Inspection interval (year)

Total cost (NTD) 0.8C 0.9C C 1.1C 1.2C 0 1 2 3 4 5 6 7 8

Fig. 12 Sensitivity of optimal inspection interval for Shihmen Dam with respect to total cost under p = 0.74, q = 0.73, and l = 30 years

1.0E+06 1.0E+07 1.0E+08 1.0E+09 1.0E+10 0 9 10 11 12 13 14 15 16 17 18 19 20

Inspection interval (year)

Total cost (NTD) 0.2 C 0.5 C C 2 C 5 C 8 7 6 5 4 3 2 1

Fig. 13 Optimal inspection interval for different breakdown cost from 0.2 to 5 C with values of p = 0.74, q = 0.73, and a mean gate breakdown time of 30 years

0 1 2 3 4 5 6 7 8 9 10 11 0.5 0.55 0.6 0.65 0.7 0.75 0.8 0.85 0.9 0.95 1 Deficiency detectability p

Optiaml inspection interval (year)

q=0.53 q=0.73 q=0.93

Fig. 14 Optimal inspection interval for different p and q with a mean gate breakdown time of 30 years

Table 4 Sensitivity interval to analysis of the inspection p, q, and C

Factor Inspection interval (unit: years) Rank

20% 10% 0% –10% –20%

p 8.7 6.6 5.3 5.1 4.2 1

q 5.7 5.4 5.3 4.9 4.7 2

(11)

inspection interval. Therefore, one can consider the uncertainties in flood frequency analysis for further study. The optimal inspection interval is determined from the expected availability; however, availability of a system, in fact, deteriorates due to external forces with time. From this point of view, a dam system may face a larger risk if inspection program is implemented infrequently, and then the users down-stream of this dam system have to pay more if dam break occurs. Conversely, the availability of a system will be more certain if inspections and repair works are conducted more frequently, but the users also have to pay more for the work required. Therefore, the uncertainty of system availability is another important topic for further study.

Acknowledgments This study was based on the work supported by the Water Resources Agency, Ministry of Economic Affair (MOEA). The assistances from the Shihmen Reservoir Administrative Bureau and other reservoir administrative bureaus are gratefully acknowl-edged. We also thank the editor and referees for very helpful sug-gestions.

References

Afshar A, Marino MA (1990) Optimizing spillway capacity with uncertainty in flood estimator. J Water Res Plan Manage ASCE 116(1):74–81

Ang AHS, Tang WH (1984) Probability concepts in engineering planning and design, vol II. Decision: risk and reliability. Wiley, New York

Askew AJ, Yeh WGY, Hall WA (1971) Use of monte carlo techniques in the design and operation of a multipurpose reservoir system. Water Resour Res 7(4):819–826

Cheng ST (1993) Statistics of dam failure. In: Yen BC, Tung YK (eds) Reliability and uncertainty analysis in hydraulic design. ASCE, New York, NY, pp 97–105

Cheng ST, Yen BC, Tang WH (1982) Overtopping risk for an existing dam. Civil Engineering Studies, Hydraulic Engineering Series No. 37, University of Illinois at Urbana-Champaign, Urbana, IL Haimes YY, Petrakian R, Karlsson PO, Mitsiopoulos J (1988) Risk analysis of dam failure and extreme floods: application of the partitioned multiobjective risk method. IWR Report 88-R-1, Environmental Systems Management Inc., Charlottesville, VA

Harr ME (1989) Probabilistic estimates for multivariate analyses. Appl Math Model 13:313–318

Hsu YC, Kuo JT (2004) Risk and uncertainty analyses of dam overtopping: Feitsui Reservoir as a case study. In: Proceedings of the 6th intl conf on hydrosci and engr (ICHE-2004), Brisbane, Australia, paper on CD-ROM, Abstract, 459–460

International Commission on Large Dams (ICOLD) (1973) Lessons from dam incidents, reduced edition, Paris

Karlsson PO, Haimes YY (1988a) Risk-based analysis of extreme events. Water Resour Res 24(1):9–20

Karlsson PO, Haimes YY (1988b) Probability distributions and their partitioning. Water Resour Res 24(1):21–29

Karlsson PO, Haimes YY (1989) Risk assessment of extreme events: application. J Water Resour Plan Manage ASCE 115(3):299–320 Kuo JT, Yeh KC, Chen JH (2004) The establishment of optimal inspection interval scheduling. Department of Civil Engineering, National Taiwan University, Report submitted to Water Resources Agency, MOEA, Taiwan (in Chinese)

Kwon HH, Moon YI (2006) Improvement of overtopping risk evaluations using probabilistic concepts for existing dams. Stoch Environ Res Risk Assess 20(4):223–237

Langseth DE, Perkins FE (1983) The influence of dam failure probabilities on spillway analysis. In: Proceedings of the conf on frontiers in hydr engr, ASCE, hydr div, Cambridge, MA, 9–12 August 1983, pp 459–464

Meon G (1992) Overtopping probability of dams under flood load. In: Kuo JT, Lin GF (eds) Stochastic Hydraulic ’92. In: Proceedings of 6th international sym, National Taiwan University, pp 99–106 National Research Council (1988) Committee on techniques for estimating probabilities of extreme floods, estimating probabil-ities of extreme floods, methods and recommended research. National Academy, Washington, DC

Pohl R (1999) Estimation of the probability of hydraulic-hydrological failure of dams. In: Proceedings of the international workshop on risk analysis in dam safety assessment, Taipei, Taiwan, pp 143– 157

Resendiz-Carrillo D, Lave LB (1987) Optimizing spillway capacity with an estimated distribution of floods. Water Resour Res 23(11):2043–2049

Tang WH, Yen BC (1991) Dam safety inspection scheduling. J Hydrol Eng ASCE 117(2):214–229

Tung YK, Mays LW (1981) Risk models for flood levee design. Water Resour Res 17(4):833–841

Tung YK, Yen BC (2005) Hydrosystems engineering uncertainty analysis. McGraw-Hill Professional, New York

Yeh KC, Tung YK (1993) Uncertainty and sensitivity analyses of pit-migration model. J Hydrol Eng ASCE 119(2):262–283

數據

Fig. 2 Scenario of dam operations
Fig. 4 Simple fault tree of dam failure due to overtopping considering malfunctioning spillway gates
Fig. 5 Flow chart for estimating economic losses due to inundation
Fig. 7 Time-dependent occurrence probability of l malfunctioning gates
+4

參考文獻

相關文件

In the course of QA inspection, assessment of the quality of the learning and teaching of individual subjects

Wang, Solving pseudomonotone variational inequalities and pseudocon- vex optimization problems using the projection neural network, IEEE Transactions on Neural Networks 17

Define instead the imaginary.. potential, magnetic field, lattice…) Dirac-BdG Hamiltonian:. with small, and matrix

Research findings from the 1980s and 90s reported that people who drank coffee had a higher risk of heart disease.. Coffee also has been associated with an increased risk of

– The futures price at time 0 is (p. 275), the expected value of S at time ∆t in a risk-neutral economy is..

b) Less pressure on prevention and reduction measures c) No need to be anxious about the possible loss.. Those risks that have not been identified and taken care of in the

• Since the term structure has been upward sloping about 80% of the time, the theory would imply that investors have expected interest rates to rise 80% of the time.. • Riskless

Topic 4 - Promotion and Maintenance of Health and Social Care in the Community 4CAspects of risk assessment and