• 沒有找到結果。

On Optimal Time-Sharing Schemes for Multi-Period HEN Designs

N/A
N/A
Protected

Academic year: 2021

Share "On Optimal Time-Sharing Schemes for Multi-Period HEN Designs"

Copied!
15
0
0

加載中.... (立即查看全文)

全文

(1)

On Optimal Time-Sharing Schemes for Multi-Period HEN Designs

Da Jiang Chuei-Tin Chang*

Department of Chemical Engineering National Cheng Kung University

Tainan, Taiwan 70101, ROC

*Corresponding author

Abstract

(2)

optimization structure of the heat-exchanger network where the capital investments usually takes account the maximum of the areas over all periods of operation. Obviously, its operation is inefficient that not all periods require so large areas to exchange the heat. Here, taken no account of how to synthesize multi-period heat-exchanger network, an equipment sharing strategy is use to decrease the capital cost of total heat-exchanger area. A mathematical programming approach is used to automatically generate the best equipment sharing structure.

Keywords: Sharing strategy, multi-period, heat-exchanger network

1. Introduction

HEN synthesis is a well-studied practical issue. Many effective design methods have already been developed on the basis of fixed process parameters. To account for seasonal variations in these parameters, Aaltola (2002) modified the MINLP model proposed by Yee et al. (1990) so as to solve the corresponding multi-period optimization problem. In a subsequent study, Chen and Hung (2004)

(3)

more than one period. Verheren and Zhang (2006) also improved the available models for the same purpose. A common feature in these studies is that a single unit was utilized to satisfy all possible heat-exchange needs of the same match. This practice is feasible only when the heat-transfer area of the selected exchanger is sufficient for the largest duty and also its operating conditions do not change significantly from one period to another. If the latter condition cannot be met, this exchanger may be inoperable in periods with much smaller duties and, furthermore, its capital investment could be unnecessarily high.

The aforementioned drawbacks of the traditional multi-period HEN designs have been circumvented in this study with time-sharing schemes. In particular, a chosen set of exchangers are allowed to be shared by more than one match in multiple periods. With this approach, it is possible not only to reduce the capital investment of a conventional network but also to improve it operability. A simple mathematical programming model has been formulated to automatically generate the best sharing structure. The proposed implementation procedure is summarized in the following sections. 2. Cost Reduction Options (Can you rewrite this section?)

Let us first assume that, in order to generate the best time-sharing scheme of a multi-period HEN design, the optimal solution of the conventional MINLP model (Aaltola, 2002; Chen and Hung, 2004;

Verheren and Zhang, 2006) can be obtained in advance, e.g., see Table 1 and Table 2. While the conceptual structure of this HEN and also the operating conditions of its embedded matches are kept intact, the total capital cost can be reduced with two types of time-sharing options:

Table 1 Feasible reorganization structure case 2 (Table 4 in Aaltola 2002)

Match Required Area in Period 1(m2) Required Area in Period 2(m2) Required Area in Period 3(m2) Required Area in Period 4(m2) Max Area (1,1,1) 0 0 0 0 0 (1,1,2) 108.9 67.5 68.6 132.4 132.4 (2,1,2) 45.7 37.4 40.5 45.7 45.7 (3,1,2) 30.8 29.7 28.5 30.8 30.8 (4,1,3) 237.6 305.9 309.2 309.1 309.2 (6,1,4) 57 137 129.4 130.1 137

Table 2 Unfeasible reorganization structure case 1 (Chen et. al 2005)

(4)

(2,2,1) 323.32 325.32 249.51 340 340

(1,1,2) 240 240 240 153.75 240

2.1 Heat duty swap

The important condition to reduce the total heat exchanger area is that two or more areas in different match and in different periods can be swapped. It contains two conditions simultaneously, one is that the largest required areas are in two different periods for two matches, the other is the required area in a match is not always larger than that in the other match among the above two periods . We give an original structure of the multi-period HEN as shown in Table 3. Assume A(a, c) and A(b, d) are the largest required areas among all periods in the Match a and Match b, respectively, A(a, c) > A(b, c) and A(b, d) > A(a, d). Obviously, if we have two exchangers with the areas of B(1) = max(A(a, c), A(b, d)), and B(2) = max(A(b, c), A(a, d)), we can reorganize these two exchangers to meet the demands of all periods for these two matches. For period c, B(1) and B(2) meet the demands of A(a, c) and A(b, c), respectively. And for period d, B(2) and B(1) meet the demands of A(a, d) and A(b, d), respectively. This simply net can reduce the area of min(A(a, c), A(b, d))- max(A(b, c), A(a, d)) for these two matches. In Table 4, two matches [(1,1,2), (6,1,4)] have the space to exchange to reduce area. However, it only reduces 132.4-130.1=2.3(m2) according to the above computer equation. If other period’s required area in Match a or Match b is larger than B(2) except for Period c and Period d, it will become more complicated to compute the reduced area, which need mathematical programming model to solve as shown in the next section.

Unfeasible reorganization structure: Any two matches has one of the following states: 1) both the largest required areas are in the same period among all the matches; or 2) if the largest required areas are not in the same period among all the matches but both the required areas in one match are larger than that of the other in the same period. Let’s take two examples to illustrate the unfeasible sharing structure.

The first case is obtained from Chen et. al (2005) as shown in Table 1. There three combinations in this HEN. Two matches [(1,2,1), (1,1,2)] meet the first state. Two matches [(1,2,1), (2,2,1)] meet the second state, and two matches [(1,2,1), (1,1,2)] meet the second state, too. Therefore this HEN is an unfeasible sharing structure.

The second case is obtained from the Table 2 in Aaltola (2002). Totally, there are 15 combinations. [(1,1,1), (2,1,2)], [(1,1,2), (3,1,2)], [(1,1,2), (4,1,3)] , [(1,1,2), (6,1,4)] , [(3,1,2), (4,1,3)] , [(3,1,2), (6,1,4)], [(4,1,3), (6,1,4)] meet the first state. And, [(1,1,1), (1,1,2)], [(1,1,1), (3,1,2)], [(1,1,1), (4,1,3)], [(1,1,1), (6,1,4)], [(1,1,2), (2,1,2)], [(2,1,2), (3,1,2)], [(2,1,2), (4,1,3)], [(2,1,2), (6,1,4)] meet the second state. So the HEN in Table 2 is not a reorganization structure, too.

Table 2 Unfeasible reorganization structure case 2 (Table 2 in Aaltola 2002) Match Required Area in Required Area in Required Area in Required

(5)

Period Period Period Period (1,1,1)

14.8

0

11.3

14

14.8

(1,1,2)

87.6

54.6

40.1

138.1

138.1

(2,1,2)

43.6

35.2

22.3

43.6

43.6

(3,1,2)

28.2

27.9

12.3

30.8

30.8

(4,1,3)

214.1

231.4

209.3

315.7

315.7

(6,1,4)

55.3

115

101

84.7

115

2.2 Exchanger area decomposition

Table 4 A scheme to illustrate the structure of original required area of heat exchanger net.

Period cPeriod d

Match a A(a, c) A(a, d)

Match b A(b, c) A(b, d)

3. Mathematical Programming Model

As mentioned previously, a mathematical programming approach can be used to automatically generate the best sharing structure. The model formulation is given below:

 

, , , , , , , , , , , , , , , . min ( ) . , , , 1, 0, , 0,1 , , , . e e m p e e e x y z e E m p e m p e m p e E m p e e m M p P e m p e m p e m M e e m p e y x st A x z A z y y z z x y z m M p P e E                 

 

(1)

(6)

heat-transfer area for match m in period p. M is the set of all match. P is the set of all period. E is the existence of the heat exchanger.

4. Examples

The capital investments of exchangers in this example are computed with a cost model adopted from literature, i.e.

( )=Cxe f C xv e

  (2) where xeis the heat-transfer area in m2 and

E

C is a cost coefficient (4333 USD/m2-yr). It is also assumed that  0.6. The sharing model equations for the examples presented in this paper have been solved

using the solver baron in the GAMS environment. The objective function is non-linear and non-convex and hence the solution of the resulting optimization model represents a local optimum. The initial value will influence the solving path and will lead the program towards a set of different local minima. It is possible to generate good sharing structures by performing several runs with different initial value. Then, the best local minimum is chosen and is presented as the solution to the heat exchanger design problem for this case.

E

xample 1

This example obtained from Isafiade and Fraser (2010) is an illustrative problem for describing the sharing model. This example consists of six matches and three periods. Every match requires a largest heat exchanger area to construct the flexible HEN. Therefore, five heat exchangers are required and the total area is 111.95 m2. We find that this HEN has a feasible sharing structure. Solving this sharing MINLP model gives the results shown in Table 3. In this sharing structure, some larger required areas are given larger base heat exchanger, and vice versa. For example, the required area at Period 2 and Period 3 in the same Match (1,2,1) are 32.1 and 11.71 m2. In order to satisfy those requests, two base heat exchangers with areas of 32.1 and 21.67 m2 are set up as show in Table 3. And then base heat exchanger with the area of 32.1 m2 is used at Period 3 in Match (2,3,4). Those adjustments will reduce the total area. Contrary to the original example the total area is 96.77 m2. All the sharing heat exchangers are suitable for the original required areas.

Table 2. The exchanger areas in Case I (Obtain from Table 4 of Isafiade and Fraser)

(7)

Total Cost= 134630.34

Figure 1 Original HEN

Table 3. Assign base exchangers to the corresponding matches in suitable periods (Case 1)

(8)
(9)
(10)

Figure 4 Period 3 3.2 Second example

(11)

swith areas of 4.15 and 23.023 m2. But actually, the heat exchanger with area 23.023 already satisfies the (2,2,2).2 , which only requires 27.173 m2. Therefore, we find out the redundant combination manually and we delete the redundant combination to simply the switch of the heat exchanger over different periods. All are marked with strikethrough.

Table 4. The exchanger areas in Case 2 (Obtain from Table 10 of Isafiade and Fraser)

Match Required Area in Period 1(m2) Required Area in Period 2(m2) Required Area in Period 3(m2) Required Area in Period 4(m2) Max Area (2,3,1) 0.377 0 4.947 0 4.947 (2,2,2) 24.849 27.173 22.111 24.975 27.173 (1,2,3) 0 4.604 4.527 5.746 5.746 (3,1,3) 0 0 0 3.801 3.801 (3,2,3) 0 0 0 0 0 (1,1,5) 49.07 54.596 53.833 47.82 54.596 (1,3,5) 16.488 25.953 25.891 0.338 25.953 Total Cost=143091.16

Table 5. Assign base exchangers to the corresponding matches in suitable periods (Case 2)

(12)

Table 6. The exchanger areas in Case 3 Match Required Area in Period 1(m2) Required Area in Period 2(m2) Required Area in Period 3(m2) Max Area (1,1,1) 14.8 15.7 14 15.7 (1,2,2) 87.6 54.6 52.3 87.6 (2,1,2) 28.2 27.9 30.8 30.8 (2,2,3) 214.1 231.4 304.6 304.6 (2,3,4) 0 143.2 0 143.2 (1,CU,5) 0 0 56.6 56.6 (2,CU,5) 100.9 108.3 105.2 108.3 Total Cost= 459923.51

Table 7. Assign base exchangers to the corresponding matches in suitable periods (Case 3)

Area (m2) S(1) S(2) S(3) S(4) S(5) S(6)   108.3 30.8 28.2 304.6 54.6 183.3 (1,1,1).1 (1,1,1).2 (1,1,1).3 (1,2,2).1 (1,2,2).2 (1,2,2).3 (2,1,2).1 (2,1,2).2 (2,1,2).3 (2,2,3).1 (2,2,3).2 (2,2,3).3 (2,3,4).2 (1,CU,5).3 (2,CU,5).1 (2,CU,5).2 (2,CU,5).3       Total Cost =418570.00

Table 8. The exchanger areas in Case 4

(13)

(2,1,2) 16.59 0 0 16.59 (2,2,2) 41.14 0 0 41.14 (3,2,1) 0 53.88 0 53.88 (1,CU,3) 14.08 14.08 14.08 14.08 (2,CU,3) 37.05 0 0 37.05 (3,CU,3) 0 61.02 0 61.02 (HU,1,0) 19.73 29.3 29.03 29.3 (HU,2,0) 0 0 8.71 8.71 Total Cost = 351804.15

Table 9. Assign base exchangers to the corresponding matches in suitable periods (Case 3)

Area (m2) S(1) S(2) S(3) S(4) S(5) S(6) 61.02 34.15 37.05 19.73 134.11 14.08 (1,1,2).1 (1,1,2).2 (1,1,2).3 (2,1,2).1 (2,2,2).1 (3,2,1).2 (1,CU,3).1 (1,CU,3).2 (1,CU,3).3 (2,CU,3).1 (3,CU,3).2 (HU,1,0).1 (HU,1,0).2 (HU,1,0).3 (HU,2,0).3 Total Cost = 253963.2 Comparison

Comparisons of the capital cost are shown in Table 10. This table show the capital cost both for original and sharing HEN. The table also gives the saving percent of the total capital cost after the implement the sharing strategy. The benefits gained from sharing heat exchanger structure are 9.23%, 8.70%, 8.99% and 27.81% for those four examples.

Table 10 Comparisons of the capital cost for original and sharing HEN

  Example 1 Example 2 Example 3 Example 4

Captical Cost, Original 134630.34 143091.16 459923.51 351804.15

Captical Cost, Sharing 122199.57 130637.46 418570.00 253963.20

(14)

5. Conclusion

Taken no attention of how to calculate the minimum heating and cooling requirements for a heat-exchanger network, this study presents a sharing strategy for the design of multi-period heat-heat-exchanger network where the required heat exchanger area are known. For a fixed match in different periods, the required heat-exchanger areas are not same. Within the overall objective of investment cost optimization of a multi-period industrial process, it is of great importance to improve the efficiency of recombining heat-exchanger network. This work gives a mathematical programming approach to automatically generate the best equipment sharing structure when there are significant changes in the environment of a plant. This paper shows the several criteria to discern the feasible heat-exchanger network to be recombined. Based on the extensive case studies performed so far, it can be observed that this proposed approach is especially effective for multi-period HEN design problems in which the process conditions vary significantly.

Sharing the available units is useful for the large temperature changes during different periods of heat exchange network. However, when the network structure is not same for different periods, it needs to lay down more pipelines to connect the HEN so that the pipeline investment costs will be increased. So in the next work, we shall take account that pipeline investment costs to find out the sharing HEN which is not only to reduce investment costs but also to easier switch.

Reference

1. Yee, T.F. and Grossmann, I.E. Simultaneous optimisation models for heat integration – II. Heat exchanger network synthesis. Comput Chem Eng. 1990, 14(10), 1165.

2. Yee, T.F., Grossmann, I.E. and Kravanja, Z. Simultaneous optimisation models for heat integration - I. Area and energy targeting and modeling of multi-stream exchangers. Comput Chem Eng. 1990, 14(10), 1165.

3. Aaltola, J. Simultaneous synthesis of flexible heat exchanger network. Appl Thermal Eng. 2002, 22, 907-918.

4. Chen, C.L. and Hung, P.S. A Novel Strategy for Synthesis of Flexible Heat-Exchange Networks. J. Chin. Inst. Chem. Engrs, 2005, 36(5), 421– 432.

5. Ma, X., Yao, P.J., Luo, X. and Roetzel, W. Synthesis of multi-stream heat exchanger network for multi-period operation with genetic/simulated annealing algorithms. Appl Thermal Eng. 2008, 28, 809 – 823.

6. Fraser, D.M., and Isafiade, A.J. Interval based MINLP superstructure synthesis of heat exchanger networks for multi-period operations. Chem Eng Res Des. 2010, 88, 1329 – 1341.

(15)

參考文獻

相關文件

• P u is the price of the i-period zero-coupon bond one period from now if the short rate makes an up move. • P d is the price of the i-period zero-coupon bond one period from now

The schedulability of periodic real-time tasks using the Rate Monotonic (RM) fixed priority scheduling algorithm can be checked by summing the utilization factors of all tasks

• The existence of different implied volatilities for options on the same underlying asset shows the Black-Scholes model cannot be literally true.

Information change: if there is any teaching hours change for employed foreign teacher during original approval period (at least 14 teaching hours per week in the original

6 Gregory Schopen, “The Good Monk and His Money in a Buddhist Monasticism of ‘the Mahāyāna Period’,” in Buddhist Monks and Business Matters: Still More Papers on

Finally, based on the experience in the test run period, the operational construction lab will be equipped with more and more suitable construction equipments and safety facilities

Corollary 13.3. For, if C is simple and lies in D, the function f is analytic at each point interior to and on C; so we apply the Cauchy-Goursat theorem directly. On the other hand,

Corollary 13.3. For, if C is simple and lies in D, the function f is analytic at each point interior to and on C; so we apply the Cauchy-Goursat theorem directly. On the other hand,