• 沒有找到結果。

Flowshop Scheduling Problem to minimize total completion time with Random and Bounded Processing Times

N/A
N/A
Protected

Academic year: 2021

Share "Flowshop Scheduling Problem to minimize total completion time with Random and Bounded Processing Times"

Copied!
10
0
0

加載中.... (立即查看全文)

全文

(1)

Flowshop scheduling problem to minimize total

completion time with random and bounded

processing times

YN Sotskov1, A Allahverdi2* and T-C Lai3 1

United Institute of Informatics Problems, Minsk, Belarus;2Kuwait University, Safat, Kuwait;3National Taiwan University, Tapei, Taiwan

The flowshop scheduling problems with n jobs processed on two or three machines, and with two jobs processed on k machines are addressed where jobs have random and bounded processing times. The probability distributions of random processing times are unknown, and only the lower and upper bounds of processing times are given before scheduling. In such cases, there may not exist a unique schedule that remains optimal for all feasible realizations of the processing times, and therefore, a set of schedules has to be considered which dominates all other schedules for the given criterion. We obtain sufficient conditions when transposition of two jobs minimizes total completion time for the cases of two and three machines. The geometrical approach is utilized for flowshop problem with two jobs and k machines. Journal of the Operational Research Society(2004) 55, 277–286. doi:10.1057/palgrave.jors.2601682

Keywords: scheduling; flowshop; uncertainty; geometrical approach; total completion time

Introduction

The deterministic (where processing times are known with certainty) k-machine flowshop scheduling problem with the minimization of total completion time has been considered for both k¼ 2 and k42 cases. Gonzalez and Sahni1proved that this problem is unary NP-hard even for the two-machine case (k¼ 2). Therefore, the main research has been focused on the development of implicit enumeration techniques and heuristics. Many researchers considered this problem for k¼ 2, see Della Croce et al,2 and Allahverdi.3

For k42, many heuristics have been proposed including Rajendran and Ziegler,4Woo and Yim,5and Allahverdi and

Aldowaisan.6 The two-machine flowshop problem has also been considered for stochastic environments, and the following two types of stochastic problems have been addressed in the OR literature. In a stochastic job problem, processing times are assumed to be random variables following certain probability distributions: mainly the exponential probability distribution has been considered. The stochastic job problem has been addressed for minimization of makespan, see Kamburowski,7and Elmagh-raby and Thoney.8 In a stochastic machine problem, processing times are usually deterministic (and fixed before scheduling), while job completion times are random variables as a result of possible machine breakdowns. Allahverdi,9and

Allahverdi and Mittenthal10 addressed the stochastic

machine problem with total completion time criterion. In this paper, we address the stochastic job problem and consider a frequent situation when it is hard to obtain exact probability distributions for random processing times and assuming a specific probability distribution (eg, exponential) is not realistic. As such, a solution obtained by assuming a certain probability distribution may not be close to the optimal solution for the realization of the process. It has been observed that although the exact probability distribu-tions of processing times may not be known before scheduling, upper and lower bounds on processing times are easy to obtain in many practical cases.

The considered problem is to minimize total completion time of n jobs jAJ¼ {1, 2, y, n} processed on k machines mAM¼ {1, 2, y, k} when only a lower bound aj,mX0 and

an upper bound bj,mXaj,mof the processing time tj,mof job j

on machine m are given before scheduling. All n jobs have the same technological route through k machines, namely, 1, 2, y, k. Using the three-field notation of Lawler et al,11this problem may be denoted as Fk|aj,mptj,mpbj,m|PCi,k.

Here-after, Ci,kmeans the completion time of the job in position i

on machine k (the last machine in the technological route), and the criterion PCi,k means minimization of total

completion time Pni¼1Ci;k. For the research on the

deterministic problem see Lawler et al11and Tanaev et al.12 It should be noted that random processing times in the problem Fk|aj,mptj,mpbj,m|

P

Ci,kare due to external forces

in contrast to scheduling problems with controllable proces-sing times. In the latter problem, the objective is to choose

*Correspondence: A Allahverdi, Department of Industrial and Manage-ment Systems Engineering, College of Engineering and Petroleum, Kuwait University, PO Box 5969, Safat 13060, Kuwait.

E-mail: [email protected]

(2)

both optimal processing times (which are under the control of a decision-maker), and an optimal schedule with chosen processing times.13–15Another related yet different problem is so-called hoist scheduling.16,17 Hoist scheduling is con-sidered in chemical and electroplating industries, where the objective is to minimize the cycle time of a repetitive process. The hoist has to travel from one tank to another one and lift or drop the job at the suitable time. Because of the nature of the chemical process, the processing time inside each tank has to be controlled within the given lower and upper bounds. In hoist scheduling, the processing times are under the control of decision-maker and are a part of the solution.

The scheduling problems with random and bounded processing times were considered in Lai et al,18and Lai and Sotskov19for jobshop with makespan criterion and in Lai et al20for jobshop with total completion time criterion. In particular, Lai et al18provided the formula for calculating the stability radius of the schedule minimizing the makespan, that is, the largest independent variations of the processing times that this schedule remains optimal without fail. In Lai et al,20 stability analysis of a schedule minimizing total completion time was involved in a branch-and-bound algorithm for solving jobshop problem J|aj,mptj,m

pbj,m|PCi.

For a two-machine flowshop problem F2|aj,mptj,m

pbj,m|Cmax, Allahverdi and Sotskov21 found sufficient

conditions when transposition of two jobs minimizes makespan. In this paper, we address the same problem as Allahverdi and Sotskov21 but with total completion time criterion rather than makespan criterion. We also address the three-machine problem with total completion time criterion. Moreover, we consider the two-job k-machine problem for any regular objective function. In contrast to Lai et al,18Lai and Sotskov19and Lai et al,20where only exponential algorithms have been derived, in this paper, we develop polynomial procedures for solving special cases of problem Fk|aj,mptj,mpbj,m|PCi,k. The next section contains

main notations and definitions. Dominance relations for flowshop with two and three machines are derived in the subsequent two sections. In the three sections following, we utilize geometrical algorithm for the case of two jobs. Concluding remarks are made in the last section.

Definitions and notations

Let tj,mdenote processing time of operation Oj,mof job jAJ

processed on machine mAM. It is assumed that pre-emption of operation Oj,mis not allowed. Although we do not know

the exact value of tj,mbefore scheduling, we know the lower

and upper bounds of feasible processing times tj,mgiven by

inequalities

aj;mptj;mpbj;m ð1Þ

Inequalities (1) define the set (polytope) T of feasible vectors t¼ (t1,1, t1,2, y , tn,k) of the processing times: T¼

{t: aj,mptj,mpbj,m, jAJ, mAM}. For a fixed sequence p¼

(j1, j2, y, jn) of n jobs, we use the notation t[i,m](p) to denote

the processing time of operation Oji,mof job jiAJ which is

located in position i, 1pipn, of the sequence p on machine mAM. Similar to tj,m, the exact value t[i,m](p) is unknown

before scheduling, and so the notations a[i,m](p) and b[i,m](p)

are used for the lower and upper bounds of processing time t[i,m](p).

Let S¼ {p1, p2, y, pn!} be a set of all permutations

(sequences) of n jobs from set J. The set S of permutation schedules is dominant for the problem of two-machine flowshop with random processing times.22Since the proces-sing times are random variables for the problem under consideration, permutation schedules are also dominant for the problem F2|aj,mptj,mpbj,m|PCi,2. However, the set of

permutation schedules is not necessarily dominant for the problem of three-machine flowshop, and for the problem with kX3 and n¼ 2.23Therefore, for the problem with two jobs and kX3 machines, we are forced to consider the whole set of active schedules.12using geometrical approach. For the three-machine case, we will consider permutation schedules since such a restriction of feasible schedules considered is commonly used both in theory and in practice.

Let pr(t) denote the schedule defined by permutation

(sequence) prAS for the fixed vector t AT of processing times

and let Ci,m(pr(t)) denote the completion time of job ji in

position i on machine m in the schedule pr(t).

Definition 1 A set of sequences S*DS is a solution to the problem Fk|aj,mptj,mpbj,m|PCi,k if for each feasible vector

tAT of processing times, the set S* contains at least one sequence prsuch that schedule pr(t) is optimal.

The whole set S of sequences is an obvious solution to the problem Fk|aj,mptj,mpbj,m|PCi,k. However if n is large, it is

hard and practically infeasible for a scheduler to choose the best sequence from a huge set S*

¼ S of candidates as the processing of jobs evolves and additional information about processing times becomes available. Therefore, it is impor-tant to minimize the cardinality of set S*which is a solution to the problem Fk|aj,mptj,mpbj,m|PCi,k. The desirable case

is to construct a solution S* with minimal cardinality. The following dominance relation is used throughout the paper. Definition 2 Sequence prAS dominates sequence puAS with respect to T if the inequality PCi,k(pr(t))pPCi,k(pu(t))

holds for any feasible vector tAT of processing times. Let sd with dA{1, 2} denote a part (subsequence) of

sequence pAS, for example, p¼ (s1, j, s2) means a sequence

of n jobs in which job j is surrounded by subsequences s1and

s2. If there are some conditions of the form tv,xXtw,z which

are sufficient for the sequence p1¼ (s1, w, v, s2)AS to

dominate the sequence p2¼ (s1, v, w, s2)AS with respect to

(3)

similar sufficient conditions for the problem Fk|aj,mptj,mpbj,m|PCi,k by replacing tv,x by bv,x and tw,z

by aw,z. More complicated sufficient conditions are derived

in the following two sections.

Two machines

Let Tj,m(p(t)) denote the sum of processing times of the

jobs in positions 1, 2 ,y, j of the sequence pAS on machine mAM. For brevity, we omit t in this notation: Tj;mðpÞ ¼Pji¼1t½i;mðpÞ; jA{1, 2 ,y, n}, mA{1, 2, y, k}.

Also let

djðpÞ ¼ Tj;1ðpÞ  Tj1;2ðpÞ; j 2 f1; 2; :::; ng;

DjðpÞ ¼ maxfd1ðpÞ; d2ðpÞ; :::; djðpÞg

ð2Þ where the equality T0,2(p)¼ 0 is assumed. Obviously, Dj(p) is

the total idle time on the second machine until the job in position j of sequence p is completed. Observe that

DjðpÞ ¼ maxfDj1ðpÞ; djðpÞg ð3Þ

If k¼ 2, the completion time of the job in position j of sequence p is given by

Cj;2ðpÞ ¼ Tj;2ðpÞ þ DjðpÞ; ð4Þ

and the total completion time for the schedule defined by sequence p (for brevity, TCT(p)) can be calculated as follows: TCTðpÞ ¼X n j¼1 Cj;2ðpÞ ¼ Xn j¼1 Tj;2ðpÞ þ Xn j¼1 DjðpÞ

Theorem 1 For the problem F2|aj,mptj,mpbj,m|PCi,2, the

sequencep1¼ (s1, w, v, s2)AS dominates the sequence p2¼ (s1,

v, w, s2)AS with respect to T if the following three inequalities

are satisfied: av,2Xbw,2, av,1Xbw,1, and aw,2Xmin{bv,1, bw,1}.

Proof Let sequence p1have job w in position t and job v in

position tþ 1, and sequence p2have job v in position t and

job w in position tþ 1. Since both sequences p1and p2have

the same jobs in positions 1, 2, y, t1 we get the following equations:

djðp1Þ ¼ djðp2Þ; j ¼ 1; 2; . . . ; t  1 ð5Þ

It can easily be shown that

djðp1Þ ¼ djðp2Þ; j ¼ t þ 2; t þ 3; . . . ; n ð6Þ

It follows from Equation (2) that dt(p1)¼ Tt1,1(p1)þ

tw,1–Tt1,2(p1), dt(p2)¼ Tt1,1(p2)þ tv,1–Tt1,2(p2), and

dtþ 1(p1)¼ Tt1,1(p1)þ tw,1þ tv,1–Tt1,2(p1)tw,2 where

Tt1,1(p1)¼ Tt1,1(p2) and Tt1,2(p1)¼ Tt1,2(p2) since both

sequences p1and p2have the same jobs in positions 1, 2, y,

t1. From the latter five equations, we obtain

dtðp1Þ  dtðp2Þ ¼ tw;1 tv;1 ð7Þ

dtþ 1ðp1Þ  dtðp1Þ ¼ tv;1 tw;2 ð8Þ

dtþ 1ðp1Þ  dtðp2Þ ¼ tw;1 tw;2 ð9Þ

It follows from Equation (7) and the hypothesis av,1Xbw,1

that

dtðp1Þpdtðp2Þ ð10Þ

regardless what feasible values tv,1and tw,1 assume.

There-fore, from Equation (5) and Inequality (10) we obtain max{Dt–1(p1), dt(p1)}pmax{Dt–1(p2), dt(p2)}. Owing to (3),

the later inequality is equivalent to

Dtðp1ÞpDtðp2Þ ð11Þ

From the condition aw,2Xmin{bv,1, bw,1} of the theorem, it

follows that either aw,2Xbv,1or aw,2Xbw,1. If aw,2Xbv,1, then

due to (8) we get

dtþ 1ðp1Þpdtðp1Þ ð12Þ

If aw,2Xbw,1, then due to (9) we get

dtþ 1ðp1Þpdtðp2Þ ð13Þ

Therefore, if either (12) or (13) holds, then due to (5) and (10) we get

maxfDt1ðp1Þ; dtðp1Þ; dtþ 1ðp1Þg

p maxfDt1ðp2Þ; dtðp2Þ; dtþ 1ðp2Þg

ð14Þ Since both sequences p1 and p2 have the same jobs in

positions 1, 2, y, t1, we get

Cj;2ðp1Þ ¼ Cj;2ðp2Þ; j ¼ 1; 2; . . . ; t  1 ð15Þ

From Equalities (3), (4), (6) and Inequality (11), it can be shown that

Cj;2ðp1ÞpCj;2ðp2Þ; j ¼ t þ 2; t þ 3; . . . ; n ð16Þ

Taking the difference between the completion times of the jobs in positions t and tþ 1 in sequences p1and p2yields

Ct;2ðp1Þ þ Ctþ 1;2ðp1Þ  Ct;2ðp2Þ  Ctþ 1;2ðp2Þ ¼ tw;2

 tv;2 þ maxfDt1ðp1Þ; dtðp1Þg

 maxfDt1ðp2Þ; dtðp2Þg

þ maxfDt1ðp1Þ; dtðp1Þ; dtþ 1ðp1Þg

(4)

By the hypothesis av,2Xbw,2and Inequalities (11) and (14),

we obtain

Ct;2ðp1Þ þ Ctþ 1;2ðp1ÞpCt;2ðp2Þ þ Ctþ 1;2ðp2Þ ð17Þ

It follows from Equations (15)–(17) that TCT(p1)p

TCT(p2) which concludes the proof. &

Obviously, Theorem 1 holds for the case T¼ {t}, that is, for the problem F2||PCi,2. Thus, the next corollary follows.

Corollary 1 For the problem F2||PCi,2, the sequence

p1¼ (s1, w, v, s2)AS dominates the sequence p2¼ (s1, v, w,

s2)AS with respect to T¼ {t} if the following three inequalities

are satisfied: tv,2Xtw,2, tv,1Xtw,1, and tw,2Xmin{tv,1tw,1}.

Next, we derive a similar dominance relation for the case of three machines. Although the two-machine case can be seen as a particular case of the three-machine case, Theorem 1 is not a particular case of Theorem 2 proven in the following section.

Three machines

Let fj(p)¼ Dj(p)þ Tj,2(p)Tj1,3(p) where T0,3(p)¼ 0, and let

Fj(p)¼ max{f1(p), f2(p), y , fj(p)}. It can be shown that

Cj;3ðpÞ ¼ Tj;3ðpÞ þ FjðpÞ ð18Þ

Thus if k¼ 3, the total completion time for the schedule defined by sequence p can be calculated as follows:

TCTðpÞ ¼X n j¼1 Cj;3ðpÞ ¼ Xn j¼1 Tj;3ðpÞ þ Xn j¼1 FjðpÞ

We consider a sequence p1¼ (s1, w, v, s2)AS, which has

job w in position t and job v in position tþ 1, and a sequence p2¼ (s1, v, w, s2)AS, which has job v in position t and job w

in position tþ 1.

Lemma 1 Equality fr(p1)¼ fr(p2) holds for r¼ 1, 2, y , t1,

and ifmax{Dt–1(p1), dt(p1), dtþ 1(p1)}pmax{Dt–1(p2), dt(p2),

dtþ 1(p2)}, then fr(p1)pfr(p2) for r¼ t þ 2, t þ 3, y , n.

Proof It is clear that fr(p1)¼ fr(p2) for r¼ 1, 2, y , t1

since both sequences p1and p2have the same jobs in the first

t1 positions. For r ¼ t þ 2, t þ 3, y , n it follows from the definition of fr(p) that fr(p1)fr(p2)¼ max{d1(p1),y, dt(p1),

dtþ 1(p1),y, dr(p1)}  max{d1(p2),y, dt(p2), dtþ 1(p2),y,

dr(p2)}.

If max{Dt1(p1), dt(p1), dtþ 1(p1)}pmax{Dt1(p2), dt(p2),

dtþ 1(p2)}, then due to Equality (6) we get fr(p1)pfr(p2). &

Lemma 2 Equality Cr,3(p1)¼ Cr,3(p2) holds for r¼ 1, 2,y,

t1. Moreover, if max{Ft1(p1), ft(p1),

ftþ 1(p1)}pmax{Ft1(p2), ft(p2), ftþ 1(p2)} and max{Dt1(p1),

dt(p1), dtþ 1(p1)}pmax{Dt1(p2), dt(p2), dtþ 1(p2)}, then

Cr,3(p1)pCr,3(p2) for r¼ t þ 2, t þ 3, y, n.

Proof Since both sequences have the same jobs in positions 1, 2,y, t1, we get Cr,3(p1)¼ Cr,3(p2) for r¼ 1, 2,y, t1.

For r¼ t þ 2, t þ 3,y, n it follows from (18) that Cr,3(p1)Cr,3(p2)¼ max{f1(p1),y, ft(p1), ftþ 1(p1),y,

fr(p1)}max{f1(p2),y, ft(p2), ftþ 1(p2),y, fr(p2)}.

If max{Ft1(p1), ft(p1), ftþ 1(p1)}pmax{Ft1(p2), ft(p2),

ftþ 1(p2)} and max{Dt1(p1), dt(p1), dtþ 1(p1)}p

max{Dt1(p2), dt(p2), dtþ 1(p2)}, then due to Lemma 1 we

get Cr,3(p1)pCr,3(p2). &

Theorem 2 For the problem F3|aj,mptj,mpbj,m|

P Ci,3, the

sequencep1¼ (s1, w, v, s2)AS dominates the sequence p2¼ (s1,

v, w, s2)AS with respect to T if the following four conditions

are satisfied: av,1Xbw,1,

av,2Xbw,2,

av,3Xbw,3,

either (aw,3Xbv,2 and aw,2Xbv,1) or (aw,3Xbw,2 and

aw,2Xbw,1).

Proof We consider the two sequences p1and p2that have

different jobs v and w in positions t and tþ 1. It follows from the hypothesis av,1Xbw,1 and either aw,2Xbv,1 or

aw,2Xbw,1, and Equations (7)–(9) that max{Dt1(p1),

dt(p1)}pmax{Dt1(p2), dt(p2)} and

maxfDt1ðp1Þ; dtðp1Þ; dtþ 1ðp1Þg

p maxfDt1ðp2Þ; dtðp2Þ; dtþ 1ðp2Þg

ð19Þ Therefore, the condition given in Lemma 1 holds. The fr(p) values for the jobs in positions r¼ t and r ¼ t þ 1

for the two sequences p¼ p1 and p¼ p2 are given as

follows: ftðp1Þ ¼Tt1;2ðp1Þ þ tw;2 þ maxfDt1ðp1Þ;dtðp1Þg  Tt1;3ðp1Þ ftðp2Þ ¼Tt1;2ðp2Þ þ tv;2 þ maxfDt1ðp2Þ; dtðp2Þg  Tt1;3ðp2Þ ftþ 1ðp1Þ ¼ þ Tt1;2ðp1Þ þ tw;2 þ tv;2 þ maxfDt1ðp1Þ; dtðp1Þ; dtþ 1ðp1Þg  Tt1;3ðp1Þ  tw;3 ftþ 1ðp2Þ ¼Tt1;2ðp2Þ þ tv;2 þ tw;2 þ maxfDt1ðp2Þ; dtðp2Þ; dtþ 1 ðp2Þg  Tt1;3ðp2Þ  tv;3

(5)

As long as both sequences have the same jobs in positions 1 through t1, we get

Tt1;2ðp1Þ ¼Tt1;2ðp2Þ; Tt1;3ðp1Þ

¼ Tt1;3ðp2Þ; and Dt1ðp1Þ

¼ Dt1ðp2Þ

From the above equations, we get

ftðp1Þ  ftðp2Þ ¼ tw;2 tv;2 þ maxfDt1ðp1Þ; dtðp1Þg  maxfDt1ðp2Þ; dtðp2Þg ð20Þ ftþ 1ðp1Þ  ftðp1Þ ¼ tv;2 tw;3 þ maxfDt1ðp1Þ; dtðp1Þ; dtþ 1ðp1Þg  maxfDt1ðp1Þ; dtðp1Þg ð21Þ ftþ 1ðp1Þ  ftðp2Þ ¼ tw;2 tw;3 þ maxfDt1ðp1Þ; dtðp1Þ; dtþ 1ðp1Þg  maxfDt1ðp2Þ; dtðp2Þg ð22Þ

It follows from the conditions av,1Xbw,1 and av,2Xbw,2

and either (aw,3Xbv,2 and aw,2Xbv,1) or (aw,3Xbw,2 and

aw,2Xbw,1), and Equalities (20)–(22) that

maxfFt1ðp1Þ; ftðp1Þg p maxfFt1ðp2Þ; ftðp2Þg ð23Þ maxfFt1ðp1Þ; ftðp1Þ; ftþ 1ðp1Þg p maxfFt1ðp2Þ; ftðp2Þ; ftþ 1ðp2Þg ð24Þ Hence, due to Inequalities (19) and (24), the conditions stated in Lemma 2 are satisfied. The completion times of the jobs in positions t and tþ 1 on the third machine are given as Ct;3ðp1Þ ¼ Tt1;3ðp1Þ þ tw;3 þ maxfFt1ðp1Þ; ftðp1Þg Ct;3ðp2Þ ¼ Tt1;3ðp2Þ þ tv;3 þ maxfFt1ðp2Þ; ftðp2Þg Ctþ 1;3ðp1Þ ¼ Tt1;3ðp1Þ þ tw;3 þ tv;3 þ maxfFt1ðp1Þ; ftðp1Þ; ftþ 1ðp1Þg Ctþ 1;3ðp2Þ ¼ Tt1;3ðp2Þ þ tv;3 þ tw;3 þ maxfFt1ðp2Þ; ftðp2Þ; ftþ 1ðp2Þg

From the last four equations, we get

Ct;3ðp1Þ þ Ctþ 1;3ðp1Þ  Ct;3ðp2Þ  Ctþ 1;3ðp2Þ

¼ tw;3 tv;3 þ maxfFt1ðp1Þ; ftðp1Þg

 maxfFt1ðp2Þ; ftðp2Þg

þ maxfFt1ðp1Þ; ftðp1Þ; ftþ 1ðp1Þg

 maxfFt1ðp2Þ; ftðp2Þ; ftþ 1ðp2Þg

Now it follows from the condition av,3Xbw,3 and

Inequa-lities (23) and (24) that

Ct;3ðp1Þ þ Ctþ 1;3ðp1Þ

pCt;3ðp2Þ þ Ctþ 1;3ðp2Þ

ð25Þ From Inequality (25) and Lemma 2, we get TCT(p1)pTCT(p2) which concludes the proof. &

Since Theorem 2 holds for the case T¼ {t}, the next corollary follows.

Corollary 2 For the problem F3||PCi,3, the sequence

p1¼ (s1, w, v, s2)AS dominates the sequence p2¼ (s1, v, w,

s2)AS with respect to T¼ {t} if the following four conditions

are satisfied: tv,1Xtw,1,

tv,2Xtw,2,

tv,3Xtw,3,

either (tw,3Xtv,2and tw,2Xtv,1) or (tw,3Xtw,2and tw,2Xtw,1).

Theorems 1 and 2 give sufficient conditions when sequence p1dominates sequence p2. Testing these conditions

may restrict solution S* for problem Fk|aj,mptj,m

pbj,m|PCi,k with k¼ 2 or k ¼ 3. If after such testing all n

jobs will be linearly ordered, then |S*|¼ 1. In general case when |S*|41, one can partition the set T in an appropriate way and then test dominance relations for new problems with smaller sets of feasible vectors of the processing times. Of course, if T is large such an approach may be time-consuming.

Since, in general, dominance relations do not yield an optimal solution, these relations are often used in an implicit enumeration technique (such as a branch-and-bound algo-rithm or a dynamic programming) or in a heuristic algorithm. When these relations are used in an implicit enumeration technique, they help in reducing the search space for the optimal solution further. In the case of a heuristic algorithm, the solution is further improved by applying the dominance relations to the solution obtained from the heuristic algorithm.

In the next section, we demonstrate an efficient geome-trical approach for the problem with two jobs, k machines and any regular criterion.

Geometrical algorithm for problem Fk|n¼ 2|U

Since the set of permutation schedules is not dominant for the considered problem with kX3 and n¼ 2, in this and the next two sections, we consider the whole set of active schedules including the set of permutation schedules as a proper subset. Note that the number of active schedules for problem Fk|n¼ 2,aj,mptj,mpbj,m|F may be equal to 2k.

For the problem J|n¼ 2|Cmax, the geometrical algorithm

(6)

developed by Szwarc,25 Hardgrave and Nemhauser26 and Brucker.27Sotskov28,29generalized the geometrical algorithm for the problem Jk|n¼ 2|F with any regular criterion F. Next, we describe this algorithm for the problem Fk|n¼ 2|F. Let TMj,mdenote the sum of processing times of job jAJ

on a set of machines {1, 2,y, m}DM:

TMj;m¼Pmi¼1tj;i; j2 J ¼ f1; 2g; 1pmpk. It is assumed

that TM1,0¼ TM2,0¼ 0. We introduce a coordinate system

on the plane x,y and draw the rectangle R with corners (0, 0), (TM1,k, 0), (0, TM2,k), (TM1,k, TM2,k), and rectangles Rm,

m¼ 1, 2, y, k, with corners (TM1,m1, TM2,m1), (TM1,m,

TM2,m1), (TM1,m1, TM2,m), (TM1,m, TM2,m). For brevity,

we call south-west corner (TM1,m1, TM2,m1) of the

rectangle Rmas SWm, north-west corner (TM1,m1, TM2,m)

as NWm, south-east corner (TM1,m, TM2,m1) as SEm, and

north-east corner (TM1,m, TM2,m) as NEm. The length of a

segment connecting points (x, y) and (x0, y0) in the rectangle

Ris defined as d((x, y), (x0, y0))¼ max{|x–x0|, |yy0|}.

An active schedule can be represented on the plane x,y as a trajectory (continuous polygonal line) t¼ [(0, 0), (x1, y1),

(x2, y2), y, (xr, yr), (TM1,k, TM2,k)] where either xr¼ TM1,k

or yr¼ TM2,k. Indeed, let a point (x, y) belong to the

trajectory t and let d be the length of the trajectory t from the point (0, 0) to the point (x, y). The coordinate x (coordinate y) of point (x, y) defines the state of processing job 1 (job 2) as follows. If SWuoxpSEu and

SWvoypNWv, uAM, vAM, then for the schedule

repre-sented by trajectory t, job 1 (job 2) is completed on the machines 1, 2, y, u1 (on the machines 1, 2, y, v1) before time d. Moreover, at time d job 1 (job 2) has been processed on machine u (machine v) during xSWu(during

ySWv) time units. Since a machine cannot process more

than one job at a time and pre-emption of an operation is forbidden, each straight segment [(x, y), (x0, y0)] of trajectory

t may be either horizontal (when only job 1 is processed) or vertical(when only job 2 is processed) or diagonal with slope of 451 (when both jobs 1 and 2 are processed simulta-neously). It is clear that a horizontal (vertical) segment can only pass along south or north (west or east) boundary of rectangle Rm, mAM, or along north and south (west and

east) boundary of rectangle R. The diagonal segment of a trajectory t can only pass either outside rectangle Rm or

through point NWm or point SEm. Problem Fk|n¼ 2|F of

finding the optimal schedule (trajectory) can be reduced to the shortest path problem in a digraph (V, A) constructed by the following algorithm. Let set V be a subset of set V0¼ {(0, 0), (TM1,k, TM2,k)},{NWm, SEm: mAM},

{(xm, TM2,k), (TM1,k, ym): mAM}.

Algorithm 1

(1) Set V¼ {(0, 0), SE1, NW1, (TM1,k, TM2,k)} and

A¼ {((0, 0), SE1), ((0, 0), NW1)}.

(2) Take vertex (x, y)AV\{(TM1,k, TM2,k)} with zero

outdegree. If (x, y)¼ SEm, then go to Step 3. If (x, y)¼ NWm,

then go to Step 4. If set V\{(TM1,k, TM2,k)} has no vertex

with zero outdegree, then STOP.

(3) Draw a diagonal line starting from vertex SEmuntil

either east boundary [(TM1,k, 0), (TM1,k, TM2,k)] of the

rectangle R is reached in vertex (TM1,k, ym) or open south

boundary (SWh, SEh) of the rectangle Rh, mþ 1phpk, is

reached. In the former case, set V:¼ V,{(TM1,k, ym)} and

A:¼ A,{(SEm, (TM1,k, ym)), ((TM1,k, ym), (TM1,k, TM2,k))}.

In the latter case, set V:¼ V,{SEh, NWh},

A:¼ A,{(SEm, SEh), (SEm, NWh)}. Go to Step 2.

(4) Draw a diagonal line starting from vertex NWmuntil

either north boundary [(0, TM2,k), (TM1,k, TM2,k)] of the

rectangle R is reached in vertex (xm, TM2,k) or open west

boundary (SWh, NWh) of the rectangle Rh, mþ 1phpk,

is reached. In the former case, set V:¼ V,{(xm, TM2,k)}

and A:¼ A,{(NWm, (xm, TM2,k)), ((xm, TM2,k),

(TM1,k, TM2,k))}. In the latter case, set V:¼ V,{SEh,

NWh}, A:¼ A,{(NWm, SEh), (NWm, NWh)}. Go to Step 2.

In order to find the optimal trajectory (ie, optimal schedule) for the problem Fk|n¼ 2|F, one can use the following algorithm.

Algorithm 2

(1) Construct the digraph (V, A) using Algorithm 1 and find all its border vertices, that is, the vertices (x, y) either of the form (xm, TM2,k) or of the form (TM1,k, ym).

(2) Construct the set of trajectories corresponding to the shortest paths in the digraph (V, A) from the vertex (0, 0) to each of the border vertices.

(3) Find a trajectory in the set constructed at Step 2 that represents a schedule with minimal value of the objective function F.

Algorithm 2 takes O(k log k) time (see Sotskov28,29). In the next section, we show how to generalize geometrical approach for the problem Fk|n¼ 2,aj,mptj,mpbj,m|F.

Problem Fk|n¼ 2, aj,mptj,mpbj,m|U

Let (Vt, At) denote digraph (V, A) constructed by Algorithm

1 for the problem Fk|n¼ 2|F with vector tAT of processing times. Let Kt be the set of all paths from vertex (0, 0) to

vertex (TM1,k, TM2,k) in the digraph (Vt, At), tAT. As

follows from Algorithm 1, the same path may belong to sets Ktconstructed for different vectors tAT of processing times

(recall that for any vector tAT, we have VtDV0). Let L¼ Ut2TLt. Notation lu(t) will be used for a trajectory in

rectangle R defined by path luAKt. Contrary to a path luAKt, trajectory lu(t) may be defined only when vector t of

processing times is fixed. Definition 1 given for permutation schedules pr(t), defined by sequences prAS, may be rewritten

for trajectories (active schedules) defined by paths as follows: A set of paths K*DK is called a solution to the problem Fk|n¼ 2, aj,mptj,mpbj,m|F if for each feasible vector tAT of

(7)

that trajectory lr(t) is optimal. Let m and m*be integers such

that mX1 and mþ m*pk.

Lemma 3 For any feasible vector tAT at step3 (at step 4) of Algorithm1, the diagonal line with origin in vertex SEm (in

vertex NWm) cannot intersect open south (west) boundaries of

rectangles Rmþ 1, Rmþ 2, y, Rmþ m*1, if and only if the

following m*inequalities hold: X mþ w1 i¼m a2;iX X mþ w1 i¼m b1;iþ 1; w¼ 1; 2; . . . ; m ð26Þ X mþ w1 i¼m a1;iX X mþ w1 i¼m b2;iþ 1; w¼ 1; 2; . . . ; m ! ð27Þ

Proof First, we consider the case m*¼ 1. For any vector tAT, trajectory of the form lu(t)¼ [(0, 0),y, SEm, y,

(TM1,k, TM2,k)], luAKt, cannot intersect open south boundary (SWmþ 1, SEmþ 1) of rectangle Rmþ 1if and only if

a2;mXb1;mþ 1 ð28Þ

Indeed, the diagonal segment of trajectory lu(t) with origin

in vertex SEm intersects open south boundary of rectangle

Rmþ 1only if t2,mot1,mþ 1. However, from (28) it follows that

t2,mXa2,mXb1,mþ 1Xt1,mþ 1. On the other hand, if Inequality

(28) does not hold, then there exists a vector tAT such that the diagonal segment of trajectory lu(t) with origin in vertex

SEmintersects open south boundary of rectangle Rmþ 1. For

the case m*A{2, 3, y, km}, we can repeat a similar argument m* times. As a result, Lemma 3 will be proven for step 3 of Algorithm 1 and vertex SEm. Owing to symmetry of

jobs 1 and 2, Lemma 3 can be similarly proven for step 4 of Algorithm 1 and vertex NWm. &

Let V ¼ U

t2TVtand A ¼ Ut2TAt. Owing to Lemma 3, we

can restrict the number of vertices from set V0which have to be included in the set V*. To restrict the number of arcs in the set A*, we can use the following Lemmas 4 and 4*where it is assumed that b1,kþ 1¼ TM1,kand b2,kþ 1¼ TM2,k. Let m,

m*and h be integers such that mX1 and h¼ m þ m*pk þ 1.

Lemma 4 For hpk, inclusions (SEm, SEh)AA* and (SEm,

NWh)AA* (for h¼ k þ 1, inclusions (SEm, (TM1,k, ym))AA*

and((TM1,k, ym), (TM1,k, TM2,k))AA*) hold if and only if the

following system of linear inequalities has a solution: X mþ w1 i¼m t2;iX X mþ w1 i¼m t1;iþ 1; w¼ 1; 2; . . . ; m ð29Þ X mþ w i¼m t2;io X mþ w1 i¼m t1;iþ 1 þ b1;h ð30Þ

ai;jpti;jpbi;j; i¼ 1; 2; j ¼ m; m þ 1; . . . ; h ð31Þ

Proof From Lemma 3, it follows that Inequalities (29) and (31) are necessary and sufficient for the existing vector tAT for which the diagonal line with origin in vertex SEm does

not intersect open south boundary of rectangles Rmþ 1,

Rmþ 2, y , Rh1. Let T*denote the set of all vectors tAT

where its components satisfy Inequalities (29) and (31). For hpk, Inequality (30) is necessary and sufficient for the existing vector t*AT*for which diagonal line with origin in vertex SEm intersects open south boundary (SWh, SEh) of

rectangle Rh. (In Figure 1, all such diagonal lines are located

in the black region.) Therefore for hpk, arcs (SEm, SEh) and

(SEm, NWh) have to be included to the set At at step 3 of

Algorithm 1 if and only if system (29)–(31) has a solution. We can prove Lemma 4 for the case h¼ k þ 1 similarly as for the case hpk. Note that for h ¼ k þ 1, Inequality (30) definitely hold due to the assumption of b1,kþ 1¼ TM1,k. &

Owing to symmetry between jobs 1 and 2, the claim analogous to Lemma 4 (we call it Lemma 4*) can be proven for arcs (NWm, SEh) and (NWm, NWh) with mX1 and

h¼ m þ m*pk, and for arcs (NW

m, (xm, TM2,k)) and ((xm,

TM2,k), (TM1,k, TM2,k)) with mX1 and h¼ k þ 1. In

particular, analogous system (29*)–(31*) of linear inequalities used in Lemma 4* instead of (29)–(31) is obtained from system (29)–(31) by replacing t2,iby t1,i, t1,iþ 1by t2,iþ 1, and

b1,hby b2,h. Using Lemmas 3, 4 and 4*one can construct the

digraph (V*, A*) containing path set K*which is a solution

to the problem Fk|n¼ 2,aj,mptj,mpbj,m|F for any regular

criterion F. To this end, we can use Algorithm 3 where Rkþ 1

denotes R. Algorithm 3

(1) Set V*¼ {(0, 0), SE1, NW1, (TM1,k, TM2,k)} and

A*¼ {((0, 0), SE1), ((0, 0), NW1)}.

(2) Take vertex (x, y)AV*\{(TM1,k, TM2,k)} with zero

outdegree. If (x, y)¼ SEm, go to Step 3. If (x, y)¼ NWm, go

to Step 4. If set V*\{(TM1,k, TM2,k)} has no vertex with zero

outdegree, go to Step 5. b1,h a2,m b2,m Rm Rh

(8)

(3) Test Inequalities (26) from Lemma 3 and define rectangle Rh with minimal h where its boundary may be

reached by the diagonal line with origin in vertex SEm. If

hpk, set V*: ¼ V*,{SEh, NWh} and A*:¼ A*,{(SEm,

SEh), (SEm, NWh)}. If h¼ k þ 1, set V*: ¼ V*,{(TM1,k,

ym)}, A*:¼ A*,{(SEm, (TM1,k, ym)), ((TM1,k, ym), (TM1,k,

TM2,k))}. Go to Step 2.

(4) Test Inequalities (27) from Lemma 3 and define rectangle Rh with minimal h where its boundary may be

reached by the diagonal line with origin in vertex NWm. If

hpk, set V* : ¼ V*,{SEh, NWh} and A*:¼ A*,{(NWm,

SEh), (NWm, NWh)}. If h¼ k þ 1, set V*: ¼ V*,{(xm,

TM2,k)}, A*:¼ A*,{(NWm, (xm, TM2,k)), ((xm, TM2,k),

(TM1,k, TM2,k))}. Go to Step 2.

(5) Solve system (29)–(31) for each vertices SEmAV* and

SEhAV* such that (SEm, SEh)eA*, 1pmohpk þ 1. If system (29)–(31) has a solution and hpk (h ¼ k þ 1), then set A*:¼ A*,{(SEm, SEh), (SEm, NWh)} (set A*:¼ A*,{(SEm,

(xm, TM2,k))}).

(6) Solve system (29*)–(31*) for each vertices NWmAV*

and NWhAV* such that (NWm, NWh)eA*, 1pmohpk þ 1. If system (29*)–(31*) has a solution and hpk (h ¼ k þ 1), then set A*: ¼ A*,{(NWm, NWh), (NWm,

SEh)} (set A*:¼ A*,{(NWm, (TM1,k, ym))}). STOP.

In Figure 2, the digraph (V*, A*) constructed by Algorithm 3 is shown for the example of the problem F5|n¼ 2,aj,mptj,mpbj,m|F with lower and upper bounds of

processing times given in Table 1. This digraph represents the set of paths K* (solution to the problem F5|n¼ 2,aj,mptj,mpbj,m|F) in the condensed form.

It is clear that Algorithm 3 takes polynomial time. Indeed, for each of vertices V*we have to test at most k Inequalities (26) at step 3, and at most k Inequalities (27) at step 4. At step 5 (step 6), for each pair of non-adjacent vertices in the constructed digraph (V*, A*) we have to solve system

(29)–(31) (system (29*)–(31*), respectively) of at most 5k linear inequalities with at most 2k variables.

Lemmas 3, 4 and 4*are valid for any regular criterion F. Next, we show how to further minimize the set K*for the total completion time.

Problem Fk|n¼ 2, aj,mptj,mpbj,m|RCi,k

Let D(lr(t)) denote the sum of the lengths of the all

horizontal and vertical segments in the part of trajectory lr(t)¼ [(0, 0), y, (x, y), (TM1,k, TM2,k)] from vertex (0, 0) to

the border vertex (x, y). Next, we show that the total completion time for the schedule presented by trajectory lr(t)

(for brevity, TCT(lr(t))) can be calculated as follows:

TCTðlrðtÞÞ ¼ TM1;k þ TM2;k þ DðlrðtÞÞ ð32Þ

If D(lr(t))¼ 0, then TCT(lr(t))¼ TM1,kþ TM2,k. If

D(lr(t))40, then each vertical (horizontal) segment of

trajectory lr(t) from vertex (0, 0) to the border vertex (x,

y) adds to the sum TM1,kþ TM2,kthe value equal to the

length of this segment since exactly one job waits in each time point corresponding to the vertical (horizontal) segment of trajectory lr(t). The length of the segment [(x, y), (TM1,k,

TM2,k)] is not added to the sum D(lr(t)) since no job waits in

each time point corresponding to this segment (one job is already completed). (x2,TM2,k) (x3,TM2,k) (x4,TM2,k) NW5 (TM1,k,TM2,k) NW2 NW3 NW4 NW1 SE2 SE3 SE4 SE5 (0,0) SE1

Figure 2 Digraph (V*, A*) constructed by Algorithm 3.

Table 1 Lower and upper bounds of processing times

Machine m m¼ 1 m¼ 2 m¼ 3 m¼ 4 m¼ 5

a1,m 2 19 8 4 12

b1,m 2 20 10 10 14

a2,m 16 3 4 2 4

(9)

From Equality (32), it follows that minimizing total completion time is equivalent to minimizing the value of D(lr(t)). For any path lwAK, we can define vector tw¼ ðtw 1;1; t w 1;2; :::; t w 1;k; t w 2;1; t w 2;2; :::; t w 2;kÞ 2 T as follows. If point SEm

or point SWmbelongs to the horizontal segment of trajectory

lw(t), we set tw1;m¼ b1;m, otherwise we set tw1;m¼ a1;m. If point

NWm or point SWm belongs to the vertical segment of

trajectory lw(t), we set tw2;m¼ b2;m, otherwise we set

tw

2;m¼ a2;m. Let notation (SEm, SEh)Alwmean that path lw

includes arc (SEm, SEh). Let SEkþ 1 denote vertex (TM1,k,

ym) and NWkþ 1denote vertex (xm, TM2,k).

Theorem 3 The set {lw} is a solution to the problem

Fk|n¼ 2,aj,mptj,mpbj,m|SCi,kif and only if the following three

conditions are satisfied:

(i) If either (SEm, SEh)Alw or (SEm, NWh)Alw, then

Inequalities(26) hold along with Xh1 i¼m b2;io Xh1 i¼m a1;iþ 1 þ b1;h ð33Þ

(ii) If either (NWm, SEh)Alw or (NWm, NWh)Alw, then

Inequalities(27) hold along with Xh1 i¼m b1;io Xh1 i¼m a2;iþ 1 þ b2;h ð34Þ

(iii) Schedule represented by trajectory lw(tw) is optimal for

the problem Fk|n¼ 2|SCi,k with vector twof processing

times.

Proof Sufficiency. First, we show that from conditions (i) and (ii) it follows that path lwis contained in the digraph

(Vt, At) constructed by Algorithm 1 for any feasible vector

tAT. We assume that (SEm, SEh)Alw. From condition (i), it

follows that Inequalities (26) and (33) hold. Thus, system of linear Inequalities (29)–(30) is satisfied for any vector tAT. Therefore, due to Lemma 3, set Atcontains arc (SEm, SEh)

for any vector tAT. Similarly if (NWm, SEh)Alw, then

condition (ii) implies that Inequalities (27) and (34) hold. Therefore, set Atcontains arc (NWm, SEh) for any vector

tAT. Arguing in a similar way for each arc in the path lw, we

conclude that the whole path lwis contained in the digraph

(Vt, At) for any vector tAT. From condition (iii) we get

inequality TCT(lr(tw)) – TCT(lw(tw))X0 for each trajectory

lr(tw) with path lr from the digraph ðVtw; AtwÞ. Therefore

due to (32), we get

DðlrðtwÞÞ  DðlwðtwÞÞX0 ð35Þ

We consider arbitrary feasible vector t¼ (t1,1, t1,2, y ,t1,k,

t2,1, t2,2, y, t2,k)AT of the processing times. Since path lwis

contained in the digraph (Vt, At), replacing twj;m¼ aj;m by

tj;mXaj;mcannot change the value D(lw(tw)) but can increase

the value D(lr(tw)). Due to the same reason, after replacing

twj;m¼ bj;m by tj;mobj;m the value D(lw(tw)) is decreased by

the maximal possible value, namely, by value bj,mtj,m.

So, taking into account (35), we get TCTðlrðtÞÞ

TCTðlwðtÞÞ ¼ DðlrðtÞÞ  DðlwðtÞÞXDðlrðtwÞÞ  DðlwðtwÞÞ

X0: To finish sufficiency proof, we have to compare trajectory lw(t) with trajectory lu(t) such that the digraph

ðVtw; AtwÞ does not contain path lu. Let trajectory lu(tw)

represent schedule with the same orders of jobs on all k machines as the schedule represented by trajectory lu(t).

(Note that the former schedule may not be active.) From condition (iii), we get inequality D(lu(tw))D(lw(tw))X0.

Arguing similarly as for trajectory lr(tw), we can show that

TCTðluðtÞÞ TCTðlwðtÞÞ ¼ DðluðtÞÞ  DðlwðtÞÞXDðluðtwÞÞ

DðlwðtwÞÞX0:

Necessity. If either condition (i) or condition (ii) is not satisfied, then due to Lemma 3 there exists feasible a vector tAT such that digraph (Vt, At) does not contain path lw.

Therefore, single-element set {lw} cannot be a solution to the

problem Fk|n¼ 2,aj,mptj,mpbj,m|SCi,k. If schedule

repre-sented by trajectory lw(tw) is not optimal for the problem

Fk|n¼ 2|SCi,kwith vector twAT(violation of condition (iii)), then set {lw} is not a solution to the problem

Fk|n¼ 2,aj,mptj,mpbj,m|SCi,k. &

Testing whether a singleton is a solution to problem Fk|n¼ 2,aj,mptj,mpbj,m|SCi,k takes O(k3) time. Indeed, we

can use Algorithm 2 for some fixed feasible vector t of the processing times and construct all optimal trajectories for the problem Fk|n¼ 2|SCi,k. Then we can test Theorem 3 for

each of the constructed optimal trajectories. Number of optimal trajectories for the problem Fk|n¼ 2|SCi,k is

restricted by the number of border vertices asymptotically restricted by O(k). It is clear that testing Theorem 3 takes O(k2) time.

For the problem F5|n¼ 2,aj,mptj,mpbj,m|SCi,5 with

bounds of processing times given in Table 1, conditions of Theorem 3 hold for the path lw¼ ((0, 0), SE1, SE2, NW3,

(x3, TM2,5), (TM1,5, TM2,5)). Owing to Theorem 3,

single-ton {lw} is a solution to the problem F5|n¼ 2,aj,mp

tj,mpbj,m|SCi,5.

Conclusion

Sufficient conditions are proven for fixing the order of two adjacent jobs in an optimal schedule for the problem Fk|aj,mptj,mpbj,m|SCi,k with n jobs and two or three

machines. Such conditions may be used to minimize solution S* of problem Fk|aj,mptj,mpbj,m|SCi,kwith kp3. It is clear

that Theorems 2 and 3 can be generalized for k43. In the previous section, necessary and sufficient conditions are proven for the existing single-element solution to the problem Fk|n¼ 2,aj,mptj,mpbj,m|SCi,k. This result can be

(10)

generalized for a jobshop problem with two jobs and other regular criterion. In this case, we need to modify Equality (32) in an appropriate way. Note that all conditions presented in Theorems 1–3 can be tested in polynomial time.

Acknowledgments—The research of the first author was partially supported by INTAS (project 00-217). The research of the second author was supported by Kuwait University Research Administration (project EM 01/01). The research of the third author was supported by NSC of Taiwan under projects NSC 89-2416-H002-039 and NSC 91-2416-H-002-006.

References

1 Gonzalez T and Sahni S (1978). Flow shop and job shop schedules. Ops Res 26: 36–52.

2 Della Croce F, Narayan V and Tadei R (1996). The two-machine total completion time flow shop problem. Eur J Opl Res 90: 227–237.

3 Allahverdi A (2000). Minimizing mean flowtime in a two-machine flowshop with sequence independent setup times. Comput Ops Res 27: 111–127.

4 Rajendran C and Ziegler H (1997). An efficient heuristic for scheduling in a flowshop to minimize total weighted flowtime of jobs. Eur J Opl Res 103: 129–138.

5 Woo HS and Yim DS (1998). A heuristic algorithm for mean flowtime objective in flowshop scheduling. Comput Ops Res 25: 175–182.

6 Allahverdi A and Aldowaisan T (2002). New heuristics to minimize total completion time in m-machine flowshops. Int J Product Econ 77: 71–83.

7 Kamburowski J (1999). Stochastically minimizing the makespan in two-machine flow shops without blocking. Eur J Opl Res 112: 304–309.

8 Elmaghraby S and Thoney KA (2000). Two-machine flowshop problem with arbitrary processing time distributions. IIE Trans 31: 467–477.

9 Allahverdi A (1999). Stochastically minimizing total flowtime in flowshops with no waiting space. Eur J Opl Res 113: 101–112. 10 Allahverdi A and Mittenthal J (1994). Two-machine ordered

flowshop scheduling under random breakdowns. Math Comput Modelling 20: 9–17.

11 Lawler EL, Lenstra JK, Rinnooy Kan AHG and Shmoys DB (1993). Sequencing and scheduling: algorithms and complexity. In: Graves SS, Rinnooy Kan AHG and Zipkin P (eds). Handbooks in Operations Research and Management Science, 4: Logistics of Production and Inventory. North-Holland, New York, pp 445–522.

12 Tanaev VS, Sotskov YN and Strusevich VA (1994). Scheduling Theory: Multi-Stage Systems. Kluwer Academic Publishers: The Netherlands, Dordrecht.

13 Ishii H, Masuda T and Nishida T (1987). Two machine mixed shop scheduling problems with controllable machine speeds. Discrete Appl Math 17: 29–38.

14 Janiak A (1988). General flow-shop scheduling with resource constraints. Int J Product Res 26: 125–138.

15 Strusevich VA (1995). Two machine flow shop scheduling problem with no wait in process: Controllable machine speeds. Discrete Appl Math 59: 75–86.

16 Lei L and Wang TJ (1991). The minimum common-cycle algorithm for cycle scheduling of two hoists with time window constraints. Mngt Sci 37: 1629–1639.

17 Chen H, Chu C and Proth JM (1998). Cyclic scheduling of a hoist with time window constraints. IEEE Trans Robotics Automat 14: 144–152.

18 Lai TC, Sotskov YN, Sotskova NY and Werner F (1997). Optimal makespan scheduling with given bounds of processing times. Math Comput Modelling 26: 67–86.

19 Lai TC and Sotskov YN (1999). Sequencing with uncertain numerical data for makespan minimization. J Opl Res Soc 50: 230–243.

20 Lai TC, Sotskov YN, Sotskova NY and Werner F. Mean flow time minimization with given bounds of processing times. Eur J Opl Res., in press.

21 Allahverdi A and Sotskov YN (2003). Two-machine flowshop minimum-length scheduling problem with random and bounded processing times. Int Trans Opl Res 10: 65–76.

22 Ku PS and Niu SC (1986). On Johnson’s two-machine flow shop with random processing times. Ops Res 34: 130–136. 23 Pinedo M (1995). Scheduling: Theory, Algorithms, and Systems.

Prentice-Hall: Englewood Cliffs, NJ.

24 Akers SB and Friedman J (1955). A non-numerical approach to production scheduling problems. Ops Res 3: 429–442.

25 Szwarc W (1960). Solution of the Akers–Friedman scheduling problem. Ops Res 8: 782–788.

26 Hardgrave WW and Nemhauser G (1963). A geometric model and graphical algorithm for a sequencing problem. Ops Res 11: 889–900.

27 Brucker P (1988). An efficient algorithm for the job-shop problem with two jobs. Computing 40: 353–359.

28 Sotskov YN (1985). Optimal scheduling two jobs with regular criterion. Design Processes Automating: 86–95 (in Russian). 29 Sotskov YN (1991). The complexity of shop-scheduling

problems with two or three jobs. Eur J Opl Res 53: 326–336.

Received April 2003; accepted November 2003 after one revision

數據

Figure 1 The case of Lemma 4 for h–m ¼ 5.
Table 1 Lower and upper bounds of processing times Machine m m ¼ 1 m ¼ 2 m ¼ 3 m ¼ 4 m ¼ 5

參考文獻

相關文件

Reading: Stankovic, et al., “Implications of Classical Scheduling Results for Real-Time Systems,” IEEE Computer, June 1995, pp.. Copyright: All rights reserved, Prof. Stankovic,

Group, R.C., Convalescent plasma in patients admitted to hospital with COVID-19 (RECOVERY): a randomised controlled, open-label, platform trial.. Lopez-Medina, E., et al., Effect

In addition, three seminars were held and in-depth interviews with 20 public-sector organizations and 20 individuals in the target sample population were

Compass and straightedge constructions, In John K.Baumgart et al (Eds), Historical topics for the mathematics classroom ( 31st yearbook)( p.193 ). Reston,

By correcting for the speed of individual test takers, it is possible to reveal systematic differences between the items in a test, which were modeled by item discrimination and

• Schemes for bounded path length minimal spanning tree with upper (and lower) bound control are presented. – With applications to

Survivor bias is that when we choose a sample from a current population to draw inferences about a past population, we leave out members of the past population who are not in

For a vehicle moving 60 mph, compute the received carrier frequency if the mobile is moving.. directly toward